how many days we should curing for
plastering,brickwork,concrete?
Answers were Sorted based on User's Feedback
Answer / senthil kumar p
Any cement based products or structures the minimum curing
period is 7 and maximum 28 days for concrete unless
otherwise you are using any curing
compound
| Is This Answer Correct ? | 115 Yes | 6 No |
Any cement based products or structures the minimum curing
period is 7 days unless otherwise you are using any curing
compound
| Is This Answer Correct ? | 79 Yes | 8 No |
Answer / ganesh mapari
7 Day for Brickwork and Plastering
14 Days for Concrete
| Is This Answer Correct ? | 36 Yes | 3 No |
Answer / udaya
It is 14 days normally. Normally we follow 14 days in summer
and 7 days in winter
| Is This Answer Correct ? | 24 Yes | 7 No |
Answer / ram mohan rai
Curring should start as soon as concrete start hardening
till at least 7 days depend upon weather condition.
| Is This Answer Correct ? | 12 Yes | 0 No |
Answer / engr.sameer
concrete need min 7 days contineous curing
| Is This Answer Correct ? | 12 Yes | 0 No |
Answer / muraliyadav
This is
depending upon
the structural
element as well
as depends on
the type of
cement can be
used in
construction
site works .the
minimum 7days
required for any
structural
element as
beams,columns,slabs
in these days
concrete did not
get full
strength only
upto 25%, if 28
days required
strength as 70
to 80% of
concrete
| Is This Answer Correct ? | 10 Yes | 12 No |
what is the least count of auto level staff
what is the use of water bar in water tank and is this an extra item in estimate?
how to calculate quantity of bricks in circular manhole with examples.
what are the functions of wall
why the cracks occurs in NP3 class Hume Pipe ? And what is bearing capacity of it?
What will be weight of 0.5mm GI sheet per sq.ft?
what should be the minimum cross sectional dimensions of column for any given loads????
what are the duties of Site Engineer in work site?
1 Answers Amarprakash Developers,
What is standard sand? What is coarse & fine sand? What is foundation? What is the seze of hooks in various Reinforced section? What is the formula of providing clear cover? What is the basic diff. between working stress & Limit state design? What is &cbc and fck? what are the primary & secondary test of water purification?
how to calculate the dry wt of sand and cement for a required design mix?for ex:M20
1 Answers Bhugan Infracon, UltraTech,
how will remove spiderweb cracking in plaster ? what the reasone of make it ?
what are the differences between opc cement and ppc cement in applications?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)