how many days we should curing for
plastering,brickwork,concrete?
Answer Posted / udaya
It is 14 days normally. Normally we follow 14 days in summer
and 7 days in winter
Is This Answer Correct ? | 24 Yes | 7 No |
Post New Answer View All Answers
what is derating factor in cable? what does it mean if derating factor is high/low in terms of thermal resistivity of soil?
Please send me the qunty. of mason/labour required in each day for different type of civil construction work?please send me ans. in my mail.my mail id is (parthamitra086@gmail.com) or here.
Used Cement & Sand in 1 Square Meter or 1 Square Feet For Brick Work 0.115mm ? (1:4) (1:6)
how many material required for brickbat water proofing of toilets.
Calculation of curtain wall of box culvert
Formula of mid span bar
What is difference between engineering stress and true stress?
use ofr concrete as per grade ?
how to convert sand in Cft to Kgs
What goals do you have in your career?
Can rice husk ash be used instead of coal fly ash for manufacture of clc/ foam concrete
The largest size of paper used in plotter to print the drawing made by Autocad .
What is the substitute of Mastic Asphalt?
what quantities of work done in terms of sq.mts/day/ of 8hrs for each varpenter (shuttering) and Steel fitter in terms of Tonnes. For slabs, Columns etc.?
5. Two long boundary walls run parallel to each other at a center to center distance of 1 meter apart. The width and height of the first wall are 0.30 m and 2.5m respectively. While those of the second are respectively 0.18m and 3.5m. Plot the distribution of vertical stress intensity due to walls on a horizontal plane, 1m below ground level. The walls have negligible depth of foundation and are made of brick masonry (y = 19.2 kN/m cu)