how many days we should curing for
plastering,brickwork,concrete?

Answer Posted / udaya

It is 14 days normally. Normally we follow 14 days in summer
and 7 days in winter

Is This Answer Correct ?    24 Yes 7 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what is derating factor in cable? what does it mean if derating factor is high/low in terms of thermal resistivity of soil?

2098


Please send me the qunty. of mason/labour required in each day for different type of civil construction work?please send me ans. in my mail.my mail id is (parthamitra086@gmail.com) or here.

1913


Used Cement & Sand in 1 Square Meter or 1 Square Feet For Brick Work 0.115mm ? (1:4) (1:6)

2002


how many material required for brickbat water proofing of toilets.

1590


Calculation of curtain wall of box culvert

5306






Formula of mid span bar

1463


What is difference between engineering stress and true stress?

662


use ofr concrete as per grade ?

1638


how to convert sand in Cft to Kgs

1478


What goals do you have in your career?

1690


Can rice husk ash be used instead of coal fly ash for manufacture of clc/ foam concrete

2009


The largest size of paper used in plotter to print the drawing made by Autocad .

1294


What is the substitute of Mastic Asphalt?

6948


what quantities of work done in terms of sq.mts/day/ of 8hrs for each varpenter (shuttering) and Steel fitter in terms of Tonnes. For slabs, Columns etc.?

1656


5. Two long boundary walls run parallel to each other at a center to center distance of 1 meter apart. The width and height of the first wall are 0.30 m and 2.5m respectively. While those of the second are respectively 0.18m and 3.5m. Plot the distribution of vertical stress intensity due to walls on a horizontal plane, 1m below ground level. The walls have negligible depth of foundation and are made of brick masonry (y = 19.2 kN/m cu)

1653