HOW TO CALCULATE LABOUR COST FOR CONCRETE WORK PER CUBIC
METER.
Answers were Sorted based on User's Feedback
Answer / sjtbehera
For M20 Grade conc.
Head mason - .05 x Rs 200 = Rs 10.00
Mason - .3 x Rs 190 = Rs 57.00
Labour - 2.5 x Rs 90 = Rs 225
______________________________________
Total amount - Rs 292.00
Add 1% for watering
This is the only Labour cost of RCC not Machinary and
pouring
| Is This Answer Correct ? | 51 Yes | 35 No |
for the rates of all labours, masssons etc we have to check
the rates from the schedule of retes of that area
| Is This Answer Correct ? | 11 Yes | 4 No |
Answer / geethu
can u explain ? Head mason - .05 x Rs 200 = Rs 10.00
Mason - .3 x Rs 190 = Rs 57.00
Labour - 2.5 x Rs 90 = Rs 225 ? wht"s mean by 0.05?
| Is This Answer Correct ? | 24 Yes | 18 No |
Answer / sjtbehera
Please tell me How many Cum can do a mason. if you know
then .05 can easily you can find, are you a civil engineer
| Is This Answer Correct ? | 14 Yes | 9 No |
Answer / santhoshselvamani
0.5 masons means
half mason charge of the day/shift
same like supervison charges
| Is This Answer Correct ? | 8 Yes | 3 No |
Answer / praman kr srivastava
Mistry I No 0.200
Beldar Nos 3.000
Bhisti No 0.900
Sundries L.S 5.500
| Is This Answer Correct ? | 5 Yes | 7 No |
HOW TO CALCULATE REINFORCMENT IN STAIRCASE CRANKED BEAM
difference between specification and method of statement
How to calculate labor requirement or requirement of labor projction for a proposed multistoried building for which quantities of different items of work has been already calculated stage wise ?
For a washout valve why are two gate valves required in normal practice?
Is it worthwhile to carry out tests on particle density of soil particles for geotechnical design?
Which IS code is saying the detail of deshuttering period?
how to determine pile length and diameter of pile is there any thumb rule?
how to calculate freeboard in under ground water tank and technical details
HOw much % of premium on DSR-2013 currently
How is rate analysis prepared for M 25 grade of concrete?
how much cement,sand,aggregate will use for 1 cum in ratio of 1:2:4.
16 Answers ARS, College School Exams Tests, Gulf Construction, HRL, mWorkspace, NCC, URC Construction,
Laboratory experiments conducted in Mumbai on a particular mix showed a strength of 33 MP a for a fully matured concrete. Find whether formworm can be removed for an identical concrete placed at Jammu at the age of 15 days when the average temperature is 60C. The stripping stress in concrete
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)