HOW TO CALCULATE LABOUR COST FOR CONCRETE WORK PER CUBIC
METER.
Answer Posted / sjtbehera
For M20 Grade conc.
Head mason - .05 x Rs 200 = Rs 10.00
Mason - .3 x Rs 190 = Rs 57.00
Labour - 2.5 x Rs 90 = Rs 225
______________________________________
Total amount - Rs 292.00
Add 1% for watering
This is the only Labour cost of RCC not Machinary and
pouring
Is This Answer Correct ? | 51 Yes | 35 No |
Post New Answer View All Answers
how much need cement bags for block work of wall approx 1000 hollow blocks 20x20x40cm
How to plan a project
What is the bowing depth after stressing of PSC Girder of various spans and various dia of strands?
What black man invented the clothes dryer?
explain the advantages of total stasion
How much cements bag (or in KG) required for 1 Sq. M concrete, for M-30 grad concrete as per CPWD and where is thr proof on site
What is a kip?
What quantity of 1.0 m3 bricks required?
Civil engineering material testing Standard results
what is the coefficient for running feet to cft coversion both area and price
What is the software used in civil engineering?
How and where are aqueducts built?
Process of pcc in wateredug
can any one tell me in detail footing estimation .. i am new here in dubai so facing lots of problem...
What is the use of water table & Kreb stone for drain