HOW TO CALCULATE LABOUR COST FOR CONCRETE WORK PER CUBIC
METER.
Answer Posted / sjtbehera
For M20 Grade conc.
Head mason - .05 x Rs 200 = Rs 10.00
Mason - .3 x Rs 190 = Rs 57.00
Labour - 2.5 x Rs 90 = Rs 225
______________________________________
Total amount - Rs 292.00
Add 1% for watering
This is the only Labour cost of RCC not Machinary and
pouring
| Is This Answer Correct ? | 51 Yes | 35 No |
Post New Answer View All Answers
How did street originate in the plumbing term street ell?
What is meaning of Canceled/Flat Beam. What is difference between them? Both type of beam can bear same load if size (width)of the flat beam is increases and depth is same as slab thickness? Kindly suggest to me.
What is reinforced concrete?
How much area, in square meters, will one liter of paint cover if it is brushed out to uniform thickness of 100 microns?
Explain the term 'Gross unit rate' and identify the items that may be included in the gross unit rate.
How to find coloumn vertical cut length floor to floor & lap + bend or anything plz clearfiy
Explain what is progress payment?
What is labor and material payment bond?
How much cement and sand are required for 1 square feet of plaster at a thickness of 15 mm at a ratio of 1:4?
please briefly explain calculating or estimating steel quantity for a RCC column?
what is E
What is componsation
What are the applications of the modulus of elasticity?
asubmerged weir is one in which the water level on the down stream side of the weir is just at the crest level below the crest level above the crest level at stamp elevation as water surface on upstream
Explain the different types of building contracts?