HOW TO CALCULATE LABOUR COST FOR CONCRETE WORK PER CUBIC
METER.
Answer Posted / sjtbehera
For M20 Grade conc.
Head mason - .05 x Rs 200 = Rs 10.00
Mason - .3 x Rs 190 = Rs 57.00
Labour - 2.5 x Rs 90 = Rs 225
______________________________________
Total amount - Rs 292.00
Add 1% for watering
This is the only Labour cost of RCC not Machinary and
pouring
| Is This Answer Correct ? | 51 Yes | 35 No |
Post New Answer View All Answers
What Are The Steps Involved In The Concreting Process, Explain?
how to calculate weight of 1.8 cum of aggregate
what are the types of dimensioning?
what is shuttering co efficient?
How to find out kg per Sft ?
What is an object snap mode?
what is the water cement ratio for plastering
Please let me know what is the simplest way of Calculating Mix Designs
What is hybrid foundation?
How much sand and cement requirement for 1 SQM 125mm thickness Brickwork
Please tell me the quantity of cement, sand, flyash, foaming agent required for 1 cubic meter of cellular lightweight concrete blocks. also , is there any admixtures required for the CLC blocks production.
please briefly explain calculating or estimating steel quantity for a RCC column?
What are the uses of alloys in daily life and how are alloys made?
I want to know the material required per Square foot in rcc roof i.e.Steel ,Cement,
What is quantity of cement and sand required for 2000sqft of tiling?