what is the stripping time of beam column & slab?
Answers were Sorted based on User's Feedback
For Beams sides only 1 day
For coloumns 1 day
For slabs span<4.50m 7 days
For slabs span>4.50m 14 days
| Is This Answer Correct ? | 14 Yes | 0 No |
what is the wait of cement in different concrete mixes from M15 TO M50
Tell me about Construction, Contraction and Expansion joints...
2 Answers Modi Builders, SMCC,
Pl answer. when we deduct 2d for cutting length of 90deg bend, whats the method of booking measurements as per IS code? whether cutting Length to be booked or something else?
WHAT DO YOU MEAN BY MIX DESIGN OF CONCRETE?NAME THE VARIOUS METHODS OF CONCRETE MIX DESIGN.EXPLAIN I.S.METHOD OF MIX DESIGN
how much percent are used 20mm,10mm?
How much wastage we considered for cement
what is the formula of calculating number of bars?
what is the initial setting time & maximum duration concrete get hardening for ordinary portland cement?
what is the dimensions of river sand truck trailer or trolly ?
what grades of reinforcement steel are available in market
what is parametre for M25 after 7 days strength
how to calculate unit weight cement ,water ,steel
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)