HOW TO CALCULATE LABOUR COST FOR CONCRETE WORK PER CUBIC
METER.
Answer Posted / naresh
.95 m/m, .68 f/m, .27 bh, .05 first class mason, .05 second
class mason, .04 mason assistant for upto 2nd floor
Is This Answer Correct ? | 22 Yes | 10 No |
Post New Answer View All Answers
What goals do you have in your career?
Please let me know about answer for my Question as "What is the maximum wastage allowable of HYSD Steel in any Bridge project as per Code and Code reference also ?
What is the significance of cost estimate knowledge for an architect?
what are the values of compressieve strenght?
what is the procedure of wet seiving. n percentage of silt in different type of soil?
Does brick grows bigger every year?
Why should pumping be not used in case of concreting works?
how much used soil in 1 brick of standard size?
How to calculate the cement plastering for circular and rectangular water storage tanks and how to calculate the area of circular and rectangular floor?? Please help me
load combinations how many types for staad design purpose?
How you read 5x3x1 #4 @ 20" 0/C in steel structure?
Formula for calculating the volume of bulb in underreamed pile
What is critical path method (c.p.m)?
how do you calculate the length of "L" of main & distribution bar for reinforcing of raft footing
Define What is the difference between routing maintenance and major maintenance in school facilities?