How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step

Answers were Sorted based on User's Feedback



How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / arunothayan umakanthan

bricks 500 nos
cement 1.88 bags
sand .266 cum

Is This Answer Correct ?    297 Yes 107 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / md.parvez

1). Brick calculation 
take brick size =200mmx100mmx100mm
convert in meter =0.2mx.1mx.1m
total volume of brick= .2x.1x.1=0.002 cum

calculate the numbers of brick for 1cum = 1cum/0.002cum= 500 numbers of bricks.

2). cement calculation
the ratio of cement mortar =1:5
sum =1+5=6
total dry mortar requried for 1 cum brick masonary=.30cum
so, 
cement = (.30x1)/6= 0.05 cum
convert in KG=.05x1440=72KG
convert in cement bag= 72/50=1.44bag.

sand calculation
sand =(.30x5)/6=.25cum
convert in kg =.25x1440=360Kg.

Is This Answer Correct ?    248 Yes 71 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / saif raza

1# Brick calculation
size of brick eg:- 200mmx10mmx10mm
1/.20x0.1x0.1 =500nos/cum.

2#Cement :- 0.3/1+5=0.05cum
:- 0.05x28.8=1.44bags.

3#Sand :- 5x0.05=0.25cum

Is This Answer Correct ?    147 Yes 78 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / er kiran gajjar

Find the 4 × 3 m concrete slab in weight kg .thickness of slab 0.15m.

~ A = 4 × 3 = 12 sq mt.

V= 12 × 0.15 = 1.8 cum


=1.8 cum × 2500 kg/cum

= 4500 kg

Is This Answer Correct ?    51 Yes 12 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / farvaris kumar

brick = 480 (as pr calculation)
.3= dry volume of brick mortar
cement = .3*28.8/total of ratio(6)
= 1.44 begs in one cum
sand = .3*quantity of sand(5)/total of ratio
= .255 for one cum

Is This Answer Correct ?    58 Yes 27 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / guest

500bricks

Is This Answer Correct ?    68 Yes 41 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / mohammed aijaz hussain

Volume of Dry Mortar = 35% of volume of Brickwork

Volume of Mortar required = 0.35 X 1 = 0.35 cu.m.

Cement required = 1/6 X 0.35 = 0.058 cu.m. = 1.67 Bags

Sand required = 5/6 X 0.35 = 0.292 cu.m.

Bricks required = 500 Nos.

Is This Answer Correct ?    64 Yes 45 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / ankush rathod

BRICK = 500
SAND = PROPORTION OF SAND IS 1:5 (1 5=6) 5/6 X 0.3=0.25CUM.
CEMENT = 1/6 X 0.3 =0.05CUM.(0.05 X 1440=72 ) 72/50=1.44
CEMENT =1.44 BAGS

Is This Answer Correct ?    24 Yes 7 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / vipin kumar

Bricks=1/volume of 1 brick

1/.23*.115*.075=504 Nos of Bricks.
But Pricitaly=475 to 485 Nos of bricks(kyoki fat layer not proper 10 0r 12mm).

Sand&Cement =100 cum B/work in 30 cum sand,
Than
cement ratio=1:5
.3/1+5=.05cum dry mortar
(1beg cement volume=(1/28.8)=.0347
Than Cement=.05/.0347=1.44 Bags
Sand =.05*5=.25cum.

Is This Answer Correct ?    28 Yes 12 No

How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work..

Answer / mohamed alfaiz

actual volume brick ------- 19cm x 9cm x 9cm = 0.0015m3 (1m3/0.0015)=666.66 nos
thickness of mortar -------- 10mm
volume of brick + mortar------- 20cm x10cm x 10cm =0.002m3 (1m3/0.002)=500 nos
=(1m3 -500/666.6)
=0.25m3 of mortar
quantity of cement required
unit wt of cement 1440kg /m3
ratio 1:5
=1440/5
=288kg/m3 x 0.25m3
72kg/50kg per bag
=1.44bag of cement
sand
0.25m3
9cft

Is This Answer Correct ?    10 Yes 1 No

Post New Answer

More Civil Engineering Interview Questions

what is curve ranging??

1 Answers  


How much quantity a carpenter can do in a day

1 Answers  


I what know about life time of frp tank plz explain about it specifications & other details

0 Answers  


What is Refuse Area ? And What is Definition ?  

2 Answers  


How much depth of excavation have to do for Highrised builldings?if Raft foundation how much,and Pile foundation how much?

1 Answers   GMR,






cement, sand, aggregate,reinforcement & concrete consumption per square feet in multi storeyed building

0 Answers  


why we used shahabad stone (ladi) in box type water proofing.what is the main roll of shahabad stone?

2 Answers  


difference between deep and shallow well?

7 Answers  


List out the diameter of series of bar for beam, column, slab and footing?

5 Answers  


how to calculate no. of cement bags consumed in 1:4 and 1:6 proportion RR Masonary and the quantity of sand also

3 Answers  


What is diversion tunnel in a dam?

0 Answers  


1:4:8 pcc calculation 591 cu.ft

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)