How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step
Answers were Sorted based on User's Feedback
Answer / suresh k
Bricks 500 no.
Cement 1.6 bags
Sand 0.3 cub-meter
| Is This Answer Correct ? | 0 Yes | 1 No |
Answer / sai ganneshh
sand=0.20cum(1cum*0.20=0.20cum)
1 cum cement= 0.20*1440/ratio last digit
if(1:5) cement =0.20*1440/5=57.6kgs
1 bag =50kg
(57.7/50=1.154bags)
| Is This Answer Correct ? | 0 Yes | 1 No |
Answer / satinder singh
brick size= .230*.115*.75
1/.230*.115*.75 = 500
10 mm mortar consider now our brick size is .240*.125*.85
1/.240*.125*.85 =500
392 = 500
500-392= 108 bricks
now 108*0.00255 = 0.275 cu m
for mortar 1:6
cement = 1/7*0.275 = 0.0393/0.0345 = 1.13 bag
sand = 6/7*0.275 = 0.023 cu m
| Is This Answer Correct ? | 1 Yes | 2 No |
Answer / gulshan vashisht from hassanpu
brick = 476 (as pr calculation)
.3= dry volume of brick mortar
cement = .3*28.8/total of ratio(6)
= 1.44 begs in one cum
sand = .3*quantity of sand(5)/total of ratio
= .250 for one cum
| Is This Answer Correct ? | 5 Yes | 7 No |
Answer / neelesh chouhan
Bricks = 500 no.
cement = 1.762
sand = 0.306 cum
| Is This Answer Correct ? | 10 Yes | 12 No |
Answer / neelesh chouhan
Bricks = 500 no.
cement = 1.762 beg
sand = 1.836 cum
| Is This Answer Correct ? | 6 Yes | 8 No |
Answer / selvaraju
brick = 390 nos as per construction
sand = 0.30m3
cement= 1.90 bags
| Is This Answer Correct ? | 5 Yes | 7 No |
Answer / sheraz
No of Bricks= volume of total brickwork / volume of brick= 1 / 0.002 =500 NO.s
Volume of mortar is 30% of volume of brickwork = 0.30 cum
dry volume of mortar = 0.30 x 1.54 = 0.462 cum
So cement Quantity = 1x0.462/1+5 = 0.077 cum
divide it by the volume of cement bag that is 0.0347 = 0.077 / 0.0347 = 2.22 bags
sand quantity = 5 x 0.462 / 1+5 = 0.385 cu m
| Is This Answer Correct ? | 0 Yes | 2 No |
Answer / bhupendra singh panwar
.230*1*1=.230
dry mortar 30%
.069/6=0.0115
cement= .35 beg
sand =.0575 cum
brick =115 nos.
| Is This Answer Correct ? | 0 Yes | 6 No |
Strength of brick?
how many cement in cubic feet of 40 kg bag white cement.
Is it necessary to apply tack coat over the primecoat. IF not what happens.answers other than 1.to superimpose the next layer(2) to adhere the layers so as to form homogenity.
how the sand fail?
What Is the Thumb rule to calculate depth and dia of pile required to carry specified load on differeent soil
50m3 concrete volume how much cement sand aggregate details radio m20grade
5 Answers L&T, Mars Planning Engineering Services, Relcon Infraprojects,
Define Chimney in Thermal power plant?
How to calculate the quantity of water in cement mortar eg. CM 1:3?
You have casted a column above your footing, and you found out it is off its location by 5cm. What would you Do?
one steel fixers how much ton steel fabrication he will do same how much tone he will binding?
4. Differentiate between NC and OC soils. Draw curves for (i) Stress vs Strain (ii) Volume charge vs Strain (iii) Pore pressure vs Strain for these soils
how much cement and sand required for 1cum rr masonry
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)