How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step
Answers were Sorted based on User's Feedback
Answer / suresh k
Bricks 500 no.
Cement 1.6 bags
Sand 0.3 cub-meter
Is This Answer Correct ? | 0 Yes | 1 No |
Answer / sai ganneshh
sand=0.20cum(1cum*0.20=0.20cum)
1 cum cement= 0.20*1440/ratio last digit
if(1:5) cement =0.20*1440/5=57.6kgs
1 bag =50kg
(57.7/50=1.154bags)
Is This Answer Correct ? | 0 Yes | 1 No |
Answer / satinder singh
brick size= .230*.115*.75
1/.230*.115*.75 = 500
10 mm mortar consider now our brick size is .240*.125*.85
1/.240*.125*.85 =500
392 = 500
500-392= 108 bricks
now 108*0.00255 = 0.275 cu m
for mortar 1:6
cement = 1/7*0.275 = 0.0393/0.0345 = 1.13 bag
sand = 6/7*0.275 = 0.023 cu m
Is This Answer Correct ? | 1 Yes | 2 No |
Answer / gulshan vashisht from hassanpu
brick = 476 (as pr calculation)
.3= dry volume of brick mortar
cement = .3*28.8/total of ratio(6)
= 1.44 begs in one cum
sand = .3*quantity of sand(5)/total of ratio
= .250 for one cum
Is This Answer Correct ? | 5 Yes | 7 No |
Answer / neelesh chouhan
Bricks = 500 no.
cement = 1.762
sand = 0.306 cum
Is This Answer Correct ? | 10 Yes | 12 No |
Answer / neelesh chouhan
Bricks = 500 no.
cement = 1.762 beg
sand = 1.836 cum
Is This Answer Correct ? | 6 Yes | 8 No |
Answer / selvaraju
brick = 390 nos as per construction
sand = 0.30m3
cement= 1.90 bags
Is This Answer Correct ? | 5 Yes | 7 No |
Answer / sheraz
No of Bricks= volume of total brickwork / volume of brick= 1 / 0.002 =500 NO.s
Volume of mortar is 30% of volume of brickwork = 0.30 cum
dry volume of mortar = 0.30 x 1.54 = 0.462 cum
So cement Quantity = 1x0.462/1+5 = 0.077 cum
divide it by the volume of cement bag that is 0.0347 = 0.077 / 0.0347 = 2.22 bags
sand quantity = 5 x 0.462 / 1+5 = 0.385 cu m
Is This Answer Correct ? | 0 Yes | 2 No |
Answer / bhupendra singh panwar
.230*1*1=.230
dry mortar 30%
.069/6=0.0115
cement= .35 beg
sand =.0575 cum
brick =115 nos.
Is This Answer Correct ? | 0 Yes | 6 No |
How much sand and cement requirement for 1 SQM 125mm thickness Brickwork
Suggest how many column, beem, etc required for 30 mtrs x 21 mtrs width x 8mtrs height for industrial shed of ground floor. I want to know the quantity of tmt steel consumption and Concrete consumption for budgeting
0 Answers Vishal Pipeline And Engineering,
1. What type of job are you holding at the moment? Name of present / last employer?
I have a slab of 20cm thickness of 20m by 4m in wich we are installing 15 tons electric panels , and we have put 4 H-shaped columns under the slab but we have done many cores in the slab which seems very normal , can you help me by telling me how to calculate the bearing capacity of the slab or give me an idea if i should increase more columns Note: load distribution area 12*1.5 m2
0 Answers First American Corporation, GS Infra, L&T, Real Sociedad,
what is diffreant types of water proofing chemical tell me please
what is a moment connection and shear connection ? where it provided ? why it provided ?
what is the relation between pitch of steel and depth of slab?
What is PQC. Means PQC
14 Answers Era Infra Engineering, L&T,
what is the dimensions of river sand truck trailer or trolly ?
how to calculate cost of raw materials of a building for 1000 sqft & also consolidated cost of labour in a 1000 sqft building
What is the lap length for tension members if you have 16 dia steel bar and a concrete fc=30.9 and steel grade60 fy=414 mpa
Used Cement & Sand in 1 Square Meter or 1 Square Feet For Brick Work 0.115mm ? (1:4) (1:6)
0 Answers L&T, Shoba Devlopers,