Procedure for conduting vector group test on power
transformers.why it is conducted?
Answers were Sorted based on User's Feedback
Purpose: The Polarity and Phase relation tests are
importent when two or more transformer are to be
paralleled.Parelleled transformer must have the same
polarity and phase relation to avoid parial or complete
short circuits.
Test Procedure:(Yyn11)
The L.V. vector will be superimposed on H.V. by connecting
1U & 2U Terminals. The three-phase voltage will be applied
to the line terminals of H.V. winding. Voltage measurement
will be done across:
1U-1V:
1V-1W:
1W-1U:
1V-2V: 1V-2W:
1W-2V: 1W-2W:
1U-2N: 1V-2N:
Checks: - 1V-2V = 1V-2W
1W-2V > 1W-2W
1U-2N + 1V-2N = 1U-1V
| Is This Answer Correct ? | 41 Yes | 14 No |
Answer / pavan
Vector group analysis is done to know the phase displacement.
| Is This Answer Correct ? | 17 Yes | 5 No |
I also wanted to know this. But as per my knowledge, Same
phase of both primary and secondary are to be shorted
before applying voltage in the answer given by Mr.
Maheshreddy.
Please let me know am I correct?
| Is This Answer Correct ? | 14 Yes | 5 No |
Answer / gunasekaran
this is important for parallel operation vector group should
be same another one is vector group is changed polarity of
the transformer also change it YNyn0 become YNyn6 if it is
changed
| Is This Answer Correct ? | 6 Yes | 1 No |
Answer / r. n. aggarwal
It is conducted to ascertain the polarity and phase
displacement.
The polarity of two transformer having the same vector
group must be same.
A further check to confirm that the polarity or phase
displacement ( vector group ) of two transformer is the
same.A single three phase LT supply is fed to the HT side
of Transformers and the same phase of the LT suppy must be
connected to the corresponding HT terminals of
Transformers .Then the voltage is checked on LT terminals
of transformers with multimeter between the same phases and
it should read almost zero.
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / anil k panjani
I would like to know the test procedure for Dyn11 vector
group and the conditions to be met for the same
| Is This Answer Correct ? | 2 Yes | 0 No |
Differentiate AC and Dc resistance
Can we use generator transformer as step down transformer? How?
In ups static switch if i gives the supply at output end it will open the circuit in stactic switch or not if it will open then how it operates.
what is the use of commutator in dc motor if we supply ac ? commutator is used to convert ac to dc.and it is used to arrange the flux in unidirectional in case of dc supply. if we give ac as supply to dc motor what is the use of commutator?
what is the ATS .And how it works.
what is the clearances between phease to phease & phease to earth in 400 kv transmission line?
Whether amorphous core transformer is available in India?.If available then up to what rating of voltage and KVA?.
0 Answers DAE, Tata Chemicals,
The D.C. spark test is applicable to single conductor cable & assemblies of insulated single conductor cables without insulation shield,metallic sheath or metalic armor?
A system absorbs 100 k J of heat and the increase in its internal energy is 100 kJ; the work done is
What is the function of lead sheath?
how to calculate current carrying capacity in power cable?
TNC switch is also available in 1NO+1NC. What does it mean ?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)