Answer / sfz ans

Assume size of bricks = 0.19m x .09m x .09m

therefore size of bricks with mortar (assuming 20mm of mortar filling betn two bricks ie: each brick gets 10mm thick layer of mortar at their face) = 0.2m x 0.1m x 0.1m

now divide the area depending upon the type of masonary work ie: Streching bond, flemish bond etc

eg:
Streching Bond for 10 sqm

no. of bricks = 10/(0.2*0.1) = 500 bricks.


Streching Bond for 1 cum work

no. of bricks = 1/(0.2*0.1*0.1) = 500 bricks

Is This Answer Correct ?    11 Yes 0 No

how to calculate the quantity of bricks..

Answer / srikanth

Normally the size of the brick is 9"x3"x4" so,we can convert into feet is 0.75x.25x.33=0.061.
1)35.28/0.061=578no.s of brick for 1Cum
2) But we have to deduction of the Mortar from it so,20% of the Mortar we can deduction forn the 578 bricks the total no.of bricks is 462 no.s

Is This Answer Correct ?    1 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

how many bricks are requir for one unit ho we will caculate

9 Answers   L&T, SPL,


What is the Oneday Productivity for 1 Skilled Carpenter and 1 Steel fixer?

2 Answers   GP Construction,


How musch steel i.e. angles, channels,and square pipes are required per square feet for a steel roof of residential two storied building?

0 Answers  


how to find quantity of concrete in PCC M15

0 Answers  


Critical Path Method is...

0 Answers  






What is the use of offset command?

0 Answers  


How we can calaculate materials required for block work(1m3) block size 33cm x 20 cm x 17 cm, mortar 1:6

3 Answers  


explain five benefits of using standard terminology in the measurement process?

0 Answers  


What are the disadvantages while using stone dust as filler in pavements?

0 Answers  


1:6 brick masonry cement and sand calculations

2 Answers   NCC,


Why do we provide development length in RCC?

4 Answers  


In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)