what is the difference between pumpable concrete and non
pumpable concrete
Answers were Sorted based on User's Feedback
Answer / balamurugan r
In order to pump a concrete using pump machine to place it
in the final position, it should have the following properties,
1.It should be M20 grade or higher
2.It should have high workability say slump value 90-120mm.
3.It should have well graded aggregates and more cement content.
4.Minimum cement content for this kind of concrete will
around 325kg/cum.
| Is This Answer Correct ? | 7 Yes | 3 No |
Answer / lalit madnawat
Pumpable concrete means
easy to workabale /having
high workability.
&
non pumpable concrete
means hard to workable/low
workability and low w/c
ratio.
| Is This Answer Correct ? | 4 Yes | 0 No |
Answer / er. amar
Pumpable concrete means the concrete mix having small size
of aggregates and having proportions of water and cement mix
in proper quantity but non pumpable has big size of
aggregates which sometimes during traveling through pipes
gets stuck at some place and due to which it creates problem
for concreting any structure.
| Is This Answer Correct ? | 3 Yes | 3 No |
Answer / ganesh
Dear one,
We are using pump in some site where we can not transit the material(concrete)l to work place, concrete used pore in the pump machine and transit rcc via pipe,
slump value should be 120mm minimum for Rcc workability,
| Is This Answer Correct ? | 0 Yes | 0 No |
weight of 1 cft 10mm, 20mm, 40mm aggregate weight of 1cft course sand
0 Answers Tanishq, Target, Yahoo,
What are the points to be considered for calculating cement reconciliation. a)Do we need to deduct the wt of cement bags b)Do we need to adjust the qty due to wt loss during transportation, loading unloading etc or else each bag can be considered as 50 kg bag c)What is the proportion of mix cover block making.
what is diffence in grade 43 & 53 of cement?
4 Answers KFC, L&T, NICE, Puravankara,
Calculation of curtain wall of box culvert
What is Rodding?
What is Architect-Prepared Contract?
how to laying tarfelt on asbestos roof for leeks water?
How do you convert wind speed into force?
As a site engineer what do you check in foundation before concreting
) Design a gussetted base for a column section consisting of one sc 250 with two cover plates 300 x 25 mm carrying an axial load of 2500 KN. The S.B.C. of soil is 250 KN/m2 and the permissible bearing pressure on concrete is 4000 KN.
In earth work 1300 cum soil how to calculate how many liters require in water
convert 1 kilo into brass
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)