Pls. help.
If a contract was awarded to a contractor in april 2012 with
steel & cement base price as rs. 45/kg & 250/bag. Now in
oct. 12 steel cement price becomes 55/kg & 290/ bag. How
escalation will be calculated? Pls. tell complete calculation
Regards,
Answers were Sorted based on User's Feedback
Answer / a.sanjeevakarna
First of all refer the contrctor agrremnt regarding the
Price escalation.
Some Govt sector accept the present rates based on the
invoices of the materials purchased and some accept only
rates approved by the govt every month.
in case of Cement and Steel in A.P. irrigation The
Escalation calculations are calculated as follows.
Cement
Date of Measeurement, Qty of concrete, Cment req as per
Design mix, Qty of Cement Consumed, Base rate + 5%,
Present rate, Present rate - Base rate, Qty of cement X
diff in price is the Escalation Amount.
Please note all above deatils sepaetared by commas are
write in Table Format.
Steel: Same as above.
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / viswanadhamklvs
Generally the PVC formula will be given in the Contract
document itself. The month in which the contractor quoted
his bid will be considered as Base month. The indices for
the commodities will be published by the office of Economic
Adviser in the web site eaindustry.nic.in. These index
values shall be substituted in the formulae given against
each commodity viz., steel and cement. In the same fashion,
labour component also shall be considered based on the index
value given by labour Beuro of India.
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / vamsi
Price escalation can done after completing of total work. As per MB the quantity of cement and steel usage have to recorded
and see the prices in the relevant work done month later total all cement qnty and steel qnty and multiply cement in Kgs/Cum using the data.
Mail me i will give u the Price Escalation Format.
vamsi.talari@gmail.com
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / jai
The prise quoted by us in the BOQ wil be the finel prise...
Is This Answer Correct ? | 0 Yes | 1 No |
Is it worthwhile to carry out tests on particle density of soil particles for geotechnical design?
Structural steel: For a thumb rule check in field, the allowable weight which can be hung down for 10mm dia mild steel rod, of yield value of 0, 25 KN/mm2 and applying a factor of safety 2.00, will be how many kg?
1sqm tile laying how much cement required?
how to calculate load for a bungalow and 1column carry how much load if the size of column ,9"*15" .....or total structure load......
from where ican get sample papers for CET-delhi 2012
Heat gain in buildings is best resisted by
6 Answers AIEEE, B Arch, JMC Projects, Unique Dream Builders,
How to construct a water sump in a rocky soil?
List out some of the checking’s, done at the completion of construction?
DEFINE M30 GRADE CONCRETE. FROM THIS QUESTION WHAT; "M" & 30?
7 Answers Descon, Northstar Homes,
Used Cement Mortar, Cement & Sand in 1 Square Meter or 1 Square Feet For 10-18mm Thick Plaster ? (1:6) (1:4)(1:3)
any book or article on pumped concrete.
How calculate the Paint quantity for a wall?