Pls. help.
If a contract was awarded to a contractor in april 2012 with
steel & cement base price as rs. 45/kg & 250/bag. Now in
oct. 12 steel cement price becomes 55/kg & 290/ bag. How
escalation will be calculated? Pls. tell complete calculation
Regards,
Answers were Sorted based on User's Feedback
Answer / a.sanjeevakarna
First of all refer the contrctor agrremnt regarding the
Price escalation.
Some Govt sector accept the present rates based on the
invoices of the materials purchased and some accept only
rates approved by the govt every month.
in case of Cement and Steel in A.P. irrigation The
Escalation calculations are calculated as follows.
Cement
Date of Measeurement, Qty of concrete, Cment req as per
Design mix, Qty of Cement Consumed, Base rate + 5%,
Present rate, Present rate - Base rate, Qty of cement X
diff in price is the Escalation Amount.
Please note all above deatils sepaetared by commas are
write in Table Format.
Steel: Same as above.
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / viswanadhamklvs
Generally the PVC formula will be given in the Contract
document itself. The month in which the contractor quoted
his bid will be considered as Base month. The indices for
the commodities will be published by the office of Economic
Adviser in the web site eaindustry.nic.in. These index
values shall be substituted in the formulae given against
each commodity viz., steel and cement. In the same fashion,
labour component also shall be considered based on the index
value given by labour Beuro of India.
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / vamsi
Price escalation can done after completing of total work. As per MB the quantity of cement and steel usage have to recorded
and see the prices in the relevant work done month later total all cement qnty and steel qnty and multiply cement in Kgs/Cum using the data.
Mail me i will give u the Price Escalation Format.
vamsi.talari@gmail.com
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / jai
The prise quoted by us in the BOQ wil be the finel prise...
| Is This Answer Correct ? | 0 Yes | 1 No |
how to calculate width and thickness of columns and beams for differnt area with example
how many hacking to be made in one sqft for concrete surface before plastering as per the IS Code
why did you choose this career
Hi all, need Staad Pro V8i tutorial
1) why bent up are provided at l/4 or l/5 distance not at l/8or l/10? 2) why extras are provided in beams at top and why upto 0.3l distance max.? 3) why chairs are provided in two way slab?
1:5:10 isme 1 kya h 5 kya h 10 kya h
DESIGN OF TRUSS ELEMENTS
I'm constructing my house, now at lintel level. I need belt concrete with laft..length - 22ft, berth- 11ft, one side laft for 2ft, *22ft length. Kindly inform me centring cost only, without material cost.
levelling least count
Machine mix is better than hand mixing to get––
what is pure bending
what size of coarce aggregate we use for slab ,column,beam and footing?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)