If a contract was awarded to a contractor in april 2012 with
steel & cement base price as rs. 45/kg & 250/bag. Now in
oct. 12 steel cement price becomes 55/kg & 290/ bag. How
escalation will be calculated? Pls. tell complete calculation

Regards,

Answer Posted / a.sanjeevakarna

First of all refer the contrctor agrremnt regarding the
Price escalation.
Some Govt sector accept the present rates based on the
invoices of the materials purchased and some accept only
rates approved by the govt every month.

in case of Cement and Steel in A.P. irrigation The
Escalation calculations are calculated as follows.

Cement
Date of Measeurement, Qty of concrete, Cment req as per
Design mix, Qty of Cement Consumed, Base rate + 5%,
Present rate, Present rate - Base rate, Qty of cement X
diff in price is the Escalation Amount.
Please note all above deatils sepaetared by commas are
write in Table Format.

Steel: Same as above.

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what is c4x light weight cement blocks

5148


I want to know the material required per Square foot in rcc roof i.e.Steel ,Cement,

1509


what is the minimum cement content for M20 & M25 as per is code -456(2000).

2703


Why nautical mile is different from statute mile?

725


what are the strength theories for yeilding and fracture materials. state the theory more suited for 1. mild steel or 2. concrete

3528






what will be the cost of thickness of 125mmor rcc measurement of 52x33.75 feet

1155


What are the basic use of runners and standards of pipelines?

676


What ingredients with% found in ppc cement??

1591


what is the minimum reinforcement provided in beams,footings,slabs? what is the minimum soil bearing capacity to design a multistorey building

1934


can we compare the combined core of DBM and BC density with average density of Lab DBM and Lab BC density

1694


How to arrive the co- efficient of all civil activities? For ex:- painting-enamel in wooden doors. co efficient is 1.8. How this is calculated

1694


04. a. Slenderness ratio…………… 1 b. If the height of a stage is 15-0 & dia. of the prop is 5, the slenderness ratio is….… 1 c. If the height of a stage is 10-0 & dia of prop is 3, the number of bracing will be…… 1

1578


What is the standard unit weight of Cast Iron pipe of 200MM Dia.(pipe specification is IS1538)

3785


Actually i am confused that how to calculate the bending moment for a semi-circular beam and curved slab.If any one have a good idea about the matter,please give the answer with a suitable example. Thank you......

1727


what s the standrd size of pvc fittings ,like elbow, bend,tee etc ? please explain with figure ?

2028