Answer / nisikanta

First of all calculate total volume of RR masonry.Then add
33% of volume more than actual volume of wet material.then
for 1:4 ;1 cement:4 coarse sand.Total volume/5=Vol of cement.
no of bags of cement=Vol of cement/.035.For 1:6 just put 6
in place of 4.

Is This Answer Correct ?    23 Yes 24 No

how to calculate no. of cement bags consumed in 1:4 and 1:6 proportion RR Masonary and the quantit..

Answer / sudhir pawar

Part A : The data :
Cement: 330/bag
Rubble : 2562/brass
Labour  :2200/brass
Sand 6500/ brass
You already know that : I brass = 100 Cft
Desired  Profit 25%

Specifications :
Rubble masonry Width 18″ to 36"
for wall compound ht upto 3′ from ground level
 in cement mortar in ratio : ( 1:5 )

Material for 1 cum:
Cement : 330*(0.45*1.57*28.8)/6= Rs.1119
Sand:   6500*0.3529*5*(0.45*1.57)/6= Rs.1350.50
Rubble: 2562*0.3529*1.45 = Rs.1311
Labour : 2200*0.3529= Rs.776

Total:                        Rs.3756 RS. 4556.50
Profit:Add@ 25%:      Rs. 1139.13
                   Total:  Rs. 5695.63  Rs/cum.

Is This Answer Correct ?    2 Yes 6 No

how to calculate no. of cement bags consumed in 1:4 and 1:6 proportion RR Masonary and the quantit..

Answer / j.edison

cement mortar1;4 1440divided by4=360kg
cement mortar 1;6 1440divided by 6=240kg

Is This Answer Correct ?    17 Yes 24 No

Post New Answer

More Civil Engineering Interview Questions

Need advice for steel in kg for RCC Slab qty 35.64m3 and Beam/ column qty 35.39m3

1 Answers  


Permissible wastage of cement as per IS code ? In which IS code I get it?

0 Answers  


how to calculate concrete pouring of foundation

2 Answers  


M25calculate of formula which in kg cement of 1cum

3 Answers  


minimum spacing of bars in column????as per code...???

7 Answers   PNC, Rajesh Associates,






Why are L-beams (cast monoloithic with slab)that usually occur at the slab edge, provided with overhangs?

1 Answers  


Why joints are provided?

0 Answers  


How many weight per 1meter cube of concrete for column.

4 Answers   JK Lakshmi Cement,


Write short note on construction programme for pile foundation.

0 Answers  


1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement Required? Brick Size 9" 4.5" 3"

48 Answers   Alcove Infrastructure, Anantha Infra, L&T, Microqual, Shoba Devlopers, SSC, UltraTech, Valdan, VVA Developers,


whats the difference between young's modulus,stress and pressure.they have same unit

3 Answers  


how many bricks in 1 one cubic meter?

4 Answers   L&T,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5084)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16631)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1094)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)