how to calculate no. of cement bags consumed in 1:4 and 1:6
proportion RR Masonary and the quantity of sand also
Answer Posted / sudhir pawar
Part A : The data :
Cement: 330/bag
Rubble : 2562/brass
Labour :2200/brass
Sand 6500/ brass
You already know that : I brass = 100 Cft
Desired Profit 25%
Specifications :
Rubble masonry Width 18″ to 36"
for wall compound ht upto 3′ from ground level
in cement mortar in ratio : ( 1:5 )
Material for 1 cum:
Cement : 330*(0.45*1.57*28.8)/6= Rs.1119
Sand: 6500*0.3529*5*(0.45*1.57)/6= Rs.1350.50
Rubble: 2562*0.3529*1.45 = Rs.1311
Labour : 2200*0.3529= Rs.776
Total: Rs.3756 RS. 4556.50
Profit:Add@ 25%: Rs. 1139.13
Total: Rs. 5695.63 Rs/cum.
Is This Answer Correct ? | 2 Yes | 6 No |
Post New Answer View All Answers
what is work of planning deptt. in any construction compny (in road project)
What you understand by richter scale?
how to estimate man power for estimating the time required for completion of a project in terms of carpenters,barbenders,masons for block work ,masons for plasteing ,unskilled labour, painters, tiles masons,plumbers and electricians for medium and high rise constructions and independent villa projects.
which are the Indian auther books for STONE COLUMN/GRANULAR PILES?
What is the cost difference between site mix and ready mix concrete per cubic meter
what is conrete grade ,how are depent on concrete grad and size of concrete?
Providing ,Cutting, bending and positioning of TMT Bar with cost of binding wire
what is mc arther pile?
show answer/ calculate-1-2-4 ratio-concrete -cement-sand- metal-water - please brief calculation
what is yield and tensile strength of steel, if steel has yeilding strength of 60 psi than how much its tensile strength?
which has high compressive strength between hollow block and brick masonry?
How to calculate volume of concrete & steel on tank foundation & ring wall ?
how many mason and labaur work for a 1 brass bricks plz let me know the calculate & how to made calculation for this and whats the formulas for this?
Define the various stages of the project planning process in construction.
Which code specifies the specification ofthe construction joints to be provided in the raft slab of a basement which is 6 m deep.what should bethe detail of such a joint?