What is the construction cost per sq foot for residential
building and give bifurcation of same?
Answer / khadar babu
Sr. No. Contract Code and Name Cost per Sqfoot % of total cost
A. Consultants
1 Architectural desigining 21.85173 1.2
2 Structural desigining 7.283911 0.4
3 Services 13.11104 0.7
7 Model making 1.098774 0.1
9 Plot Survey 0.137347 0.0
Total 43.83311 2.4
B. Civil Works
1 Excavation 15.96403 0.9
2 Antitermite treatment 0.106861 0.0
3 Sub structure Waterproofing, 3.965101 0.2
4 RCC works, Blockwork, Plaster, Misc civil works
966.7697 52.0
Total 986.8057 53.1
C. Finishing Works
1 FLOORING 142.01 7.6
2 Kitchen Platform with Sink 21.41376 1.2
3 Entrance lobby & signage 9.15645 0.5
4 Wood works 67.81992 3.6
5 Waterproofing 12.74205 0.7
6 Gypsum Plaster 36.52273 2.0
7 P.O.P false ceiling 6.498941 0.3
8 External Painting 20.82378 1.1
9 Internal Painting 21.26266 1.1
10 staircase painting 1.912218 0.1
11 Lift Shaft Painting 0.345885 0.0
12 Duct Painting 2.53158 0.1
13 Ceiling paint 7.623122 0.4
14 Aluminum Window 46.1979 2.5
17 M.S Railing 11.16349 0.6
18 Façade work 6.190976 0.3
Total 419.6929 22.6
D. Services
1 Plumbing& pumping 51.57279 2.8
2 CP Sanitary (Jaquar & Roca) 44.45325 2.4
3 Firefighting 23.43493 1.3
4 Electrical 76.44474 4.1
5 Lifts 82.40805 4.4
6 IBMS 16.33613 0.9
7 Solar water system 4.395096 0.2
8 DG Set 6.592644 0.4
Total 305.6376 16.4
Initial Total (A+B+C+D) 1755.969 94.4
Site eastablishment 33.01863 1.8
Electrical & water charges 1.5% 26.33954 1.4
Contingenices for temp. works 17.55969 0.9
EHS budget 8.779847 0.5
Construction Cost / Sft 1859.227 100.0
Is This Answer Correct ? | 3 Yes | 0 No |
How to take cutting length of Stirrups when 10 leg has given Size is 1200x1200
what is anchorage length,lap length and (dont remember the last one)
Project at andheri west mumbai total area of 116000 sq ft near by..Please help me out for quotation plan is ready basic details are with me , please help me out .I will mail u in autocad also.
how many men days of loburs and masons are requirete for 1 cum,pcc (1:2:4),Pcc(1:3:6) and Pcc(1:4:8) thanking you
how much cement and sand 1:6 plastering
What is the usage of zoom command?
What is the amount of cement,sand and course aggregate(jully)(in kgs) required for the RCC of an area of 450 square feet and 5 inch depth if the concrete mixing ratio is 1:2:4(cement:sand:jully)?your answer will be very helpful.
How to test the quality of Ready Mix M20 concrete (1:1.5:3) before casting at site when lorry arrives? Are there any methods?
how you calculate the qty. of cement ,sand,aggregate from proportion 1:2:4 M15
what is Tsunami. explain it's formation.
how to calculate labour strength for work for RCC,brickwork,blockwork,in &out plaster,flooring,dado,door frame & shutter,painting etc for constructing highrise building?
i have four storeyed rcc building.basement of the building is around 34 years old.it does not have pillar support.it is having lintel steel support at every 7 feet of construction. how long this building will lost long . can any body help me in this regard