what is the formula to calculate isolated footing
Answers were Sorted based on User's Feedback
Answer / rethina kumar
isolated sloped footing
flat portion : L X B X D = VOLUME1
SLOP PORTION : A1+A2+ (A1 X A2 ROOT)X H/3 = VOLUME2
VOLUME = V1+V2
| Is This Answer Correct ? | 254 Yes | 34 No |
Answer / chelladurai
V=LxBxd+((h/6x(A1+A2+4Am))
where
d= base height
h=total height - base height
A1= bottom area
A2=top area
Am= mean of top and bottom area
| Is This Answer Correct ? | 59 Yes | 16 No |
Answer / sanjay pati
1ST_ FORNULA :L*B*H +A1+A2+A1*A2 RA ROOT OVER
*H/3
| Is This Answer Correct ? | 29 Yes | 11 No |
Answer / vignesh
d+(D-d)/2*length*bradth
d=clear depth
D=overall depth
| Is This Answer Correct ? | 29 Yes | 17 No |
Answer / mayank bansal
H(A1+A2)/2
It can also be used.
It mainly depends up on client that which formula to be used in the starting of the projects.
| Is This Answer Correct ? | 18 Yes | 8 No |
Answer / pawan kumar
V=LxBxd+((h/6x(A1+A2+4Am))
where
d= base height
h=total height - base height
A1= bottom area
A2=top area
Am= mean of area at mid section
| Is This Answer Correct ? | 8 Yes | 5 No |
Answer / mohammad razauddin
Flat portion : L X B X D = VOLUME1
ISOLATED PORTION : A1+A2+ (A1 X A2 ROOT)X H/3 = VOLUME2
VOLUME = V1+V2
where
A1= bottom area
A2=top area
| Is This Answer Correct ? | 4 Yes | 2 No |
Manpower required for de shuttering of conccrete slab
How we can calculate the quantity of sand, & cement, & also aggregate for a slab. Length 25'/3.28 = 7.62 Mtr width 20'/3.28 = 6.09 Mtr depth 6" /3.28 = 0.152 Mtr
What is meant by Crystal Concrete?
What is meaning of Canceled/Flat Beam. What is difference between them? Both type of beam can bear same load if size (width)of the flat beam is increases and depth is same as slab thickness? Kindly suggest to me.
How to find out kg per Sft ?
How is the strength of cement measured?
can any one explain structural behaviour of trapezoidal combined footing?
what is tension column?
0 Answers Wah Engineering College,
Explain the importance of moment of inertia?
20. Do you adapt easily to new environment, job?
cud any one send me tech quest paper(civil engg) at tarizus@yahoo.com
beam top main reinforcement(25mm) was drilled off by mistakely when making drill hole for dummy columns. any one can give useful information for this issue or related code or websites.
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)