Answer / manu

1. by using under ground water in hot whether
2. by steam curing, in cold whether

Is This Answer Correct ?    9 Yes 1 No

how we control the temperature during concreting ?..

Answer / arvindrai

1))By providing temperature bars in concreting section
2)) Providing of Ice pieces at time of mixing

Is This Answer Correct ?    8 Yes 2 No

how we control the temperature during concreting ?..

Answer / sjtbehera

ok we are going to mix admixture for that, but if our
concrete mixer is place near by we can handle this. main
cause of higher temp. is water evapouration. i saw mixing
of ice for that.

Is This Answer Correct ?    2 Yes 0 No

how we control the temperature during concreting ?..

Answer / abinash chandra giri

During concrete in case of
normal weather condition
we must used underground
water/drinking water.if hot
weather condition we must
used ice but we should
follows the is 7861.in cold
season we must used hot
water.

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

we have a bore well 275 depth & water is deliver at distance of 1000 feet from the borewell here iam not include the distance of depth and the deliver water horizontally at our reserviour tank on ground level

0 Answers  


What's is mean by survey

1 Answers  


How many times we can use Fresh bentonite ford wall execution? Would like to know the clear concept of recycling. After flushing can we use it for another time time for flushing? Or we have to use it for for excavation only?

0 Answers   bsmcpl,


2nd and 4rt angle elevation used in which country ?

0 Answers   L&T,


what is the difference between sill beam,Tie beam and plinth beam?

2 Answers   L&T,






what are the types of bricks? & what is strength of this type?

1 Answers  


quantity of sand and cement for 10m2 plastering 10mm thick for the ratio of 1:4,1:3and its leabour data

0 Answers  


what is the difference between factor of safety and partial safety factor.??

2 Answers   KJH, NTPC,


form work including the props can be removed from beams only after

1 Answers  


What are the different grades of concrete & their ratios?

3 Answers  


3 Why do you want to work at our company?

1 Answers   Hyundai,


what is the creep in concrete

4 Answers   L&T,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5084)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16631)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1094)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)