In Earth work compaction
How u calculate
How many liters of water required,for compaction of ordinary
soil for one Cu.m.
Answers were Sorted based on User's Feedback
Answer / bijaya kumar behera
ex; water required for 200 mts road??
ans: volume of earth= 200 x 7 x 0 .2 = 280 cum
% OMC = 7 %
After Soil testing NMC = 5% (achived)
So required mc = 7 - 5 = 2 %
for air evaporation add 1%
2+1 = 3 %
water required in earth volume = 280 x 3 % = 8.4 cum
per cum reqd quantity of water 1000 ltr
so total water reqd = 8.4 x 1000 = 8400 ltr
| Is This Answer Correct ? | 20 Yes | 4 No |
Answer / hiren thakkar
For and e.g. Qty of earth work = 9,60,000 cum.
% OMC = 12.5
After soil test % OMC comes as per laboratory test = 8 to
9% ( say 8.9 %).
So OMC now =12.5 -8.9 = 3.6 % ( usually Depending on the
soil type, an in-situ moisture content deviating 2% to 4%
from the optimum moisture content as determined from the
Proctor test, may create impossible conditions to achieve
the required compaction).i.e 3.6 % is ok.
now Qty = 9,60,000 x 3.6/100 = 34560 cum or 34560000 lit
water required.
Now add evaporation losses @ 10%.
so now the exact vol of water required for compaction of
earth work is 3,80,16,000 lit.
| Is This Answer Correct ? | 31 Yes | 21 No |
Answer / hiren n. thakkar
Determination of Water to Be Added
If the moisture content of the soil is less
than optimum, the amount of water to be
added for efficient compaction is generally
computed in gallons per square yards. The
computation is based on the dry weight of soil
contained in a compacted layer. For example,
assume that the soil is to be placed in 6-inch,
compacted layers at a dry weight of 120 pcf.
The moisture content of the soil is determined
to be 5 percent while the OMC is 12 percent.
Assume that the strip to be compacted is 40
feet wide. Compute the amount of water that
must be added per 100-foot station to bring
the soi1 to optimum moisture. The following
formula applies:
{Desired Density (pcf)x W(desired)-W (actual)/100}x Vol.
(cu.ft)x 1gal./8.33lb
Substituting in the above formula from the
conditions given:
[120(pcf)x 12-5/100]x 100ft x 40ft x 0.5ft x 1gal/8.33lb
= 2017 gal/station.
If either drying conditions or rain conditions
exist at the time work is in progress, it may be
advisable to either add to or reduce this quantity
by up to 10 percent.
Substituting in the above formula from the
conditions given:
If either drying conditions or rain conditions
exist at the time work is in progress, it may be
advisable to either add to or reduce this quantity
by up to 10 percent.
| Is This Answer Correct ? | 4 Yes | 5 No |
How many number of bricks required for 1 cum & how much mortar quantity require for 1 cum
22 Answers Assurance, Campus Interview, R Tech Developers, Ramdev Construction, Synergy,
Quantity of cement in kgs for different proportions and different thickness in plastering work per 1 sq.m. And how to estimate this quantities.
2 Answers Al-Jaber, IVRCL, L&T,
What are the strongest shapes in building?
why distibuters used in rcc slsb
what is the stirrups? and which condition it is used?
What is the standard brick size in India(IS)
why we use 19x9x9and 20x10x10 but not other
how much one carpenter can doing shuttering of slab in one day
What do we mean by partial moment release ??
what is the anchorage length of reinforcement.
How many types of traps are used?
what are the criterias for designing a school lab? for e.g a chem lab.Does it depend on room size or no. of students?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)