Contrete reaches its full strength in 28 days. Then, why
are we removing shutter in 7/ 14 days?
Answers were Sorted based on User's Feedback
Answer / v.kapil
Concrete get its 50 % strength in 3 days and 66.6% in 7 days
with OPC grade of cement, we designed our structure for
full load including of factor of safety but actually such
loads never come structure in its whole life span, only 40-
50% loads ware accoured during construction so we can
remove our form work after 7-10 days but after confirmation
of cube results of 7 days.
| Is This Answer Correct ? | 15 Yes | 0 No |
Answer / mhbkpr
We cannot deshutter in all type of concrete works. for e.g
footing, plinth, beam sides like we can remove within this.
But roof slab likes we need provide back proping before
removing.
| Is This Answer Correct ? | 3 Yes | 1 No |
Answer / m.haseeb yaquobi
becuase it reache more then 50% of its full strenght
| Is This Answer Correct ? | 3 Yes | 3 No |
Answer / saif raza
As deshuttering period is desrcibe in IS code for diffrent
structural member.
for deshutering purpose minimum strength required is
between 65 to 75% & concrete gain more then 65% atseven
days so it is safe to remove.
| Is This Answer Correct ? | 2 Yes | 2 No |
Answer / ankit
concrete achive its full stenghth in 28 days.while minimum
strength accrd. IS CODE is 7day strngth.
in field where the cost of construction is low,
shuttering / formwork is many a times removed even after
two to three days.only intial strenght matters.
| Is This Answer Correct ? | 6 Yes | 8 No |
Define Finite element method (FEM)
wht is off shore structure
which is the cheapest type of temporary flooring(say for using 6 months on)?
what is the types of surveying?which type of survey carrying for type of work?
significance of specific surface area of particles?
what is the tensile strength of 10swg and 8swg gabion wire?
volume of one cement bag
4 Answers Grand Peaks, Omace, Swasudha Infra,
IN Compression testing machine 1division =10KN ,then what is compressive strength of 100*100 mm cubes at a load of 320 KN
How many Steel used in 1 cum tower foundation
How do you find the difference between 53&43 grade cement in site?
asubmerged weir is one in which the water level on the down stream side of the weir is just at the crest level below the crest level above the crest level at stamp elevation as water surface on upstream
Can you pl explain the procedure steps of singly and doubly reinforced beams in limit state method
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)