Contrete reaches its full strength in 28 days. Then, why
are we removing shutter in 7/ 14 days?
Answer Posted / saif raza
As deshuttering period is desrcibe in IS code for diffrent
structural member.
for deshutering purpose minimum strength required is
between 65 to 75% & concrete gain more then 65% atseven
days so it is safe to remove.
| Is This Answer Correct ? | 2 Yes | 2 No |
Post New Answer View All Answers
WHAT IS YOUR CURRENT SALARY
how water proof chemicals act in concrete to avoid leek?
How will be cutting in timber plate size 600*400 column size
mix design procedure for 1:6 cement mortar
what is the price of a cubic meter of concrete on international market?
01. a. Diagram of a slump cone…………… 1 b. Size of Slump Cone…………… 1 c. Volume of a slump cone by av. Dia method…………… 1 d. Volume of a slump cone by av. area method…………… 1 e. Volume of a slump cone by frustrum method …………… 1 f. Angles of slump cone …………… 1 g. Slump measured by slump cone due to…………… 1 h. Slump does not measured by cylinder / cube due to …………… 1 i) ii) i. Slump cone is to be filled in……………………..Layers.
How can we demolish concrete beams?
Why are steel plates inserted inside bearings in elastomeric bearings?
wat would be the probable interview questions and GD topics for IOCL exam?
how to control PQI (Project Quality Index)
pls tell me , what is the water content
in one SQM plaster how much Cement and sand consumed in ratio 1:4
cement mortor 1:5 for 30 m2 12 mm tk plastering so how to calcualte its rate
what is the method used for marking of cantilevers in hirise buildings by using theodolite
What are the applications of modulus of elasticity?