Contrete reaches its full strength in 28 days. Then, why
are we removing shutter in 7/ 14 days?
Answer Posted / ankit
concrete achive its full stenghth in 28 days.while minimum
strength accrd. IS CODE is 7day strngth.
in field where the cost of construction is low,
shuttering / formwork is many a times removed even after
two to three days.only intial strenght matters.
| Is This Answer Correct ? | 6 Yes | 8 No |
Post New Answer View All Answers
Design a rectangular channel.
what is relation between SPT N value and driving piles after conducting a soil test?
What is unit weight of roadway layer.. 1.bitumen 2.sand 3.soil 4.concrete 5. aggregate give me some reference for this answers
What is 1/8 on the architect ruler denotes?
what is conventional shuttering rate per square feet of built up area? what is Mivan shuttering rate per square feet of built up area? what is coupler shuttering rate per square feet of built up area?
1:4:8 pcc calculation 591 cu.ft
I'm preparing to to build a simple house, but i don't know how to calculate how much cement, gravel and sand and hollow blocks i need to prepare. How many pcs of 4" or 6" hollow blocks I need for my planned 3mx6m house? thanks.
Thumb rule for steel qty for 1m2 in kg/m2 column slab footing beam
how to determine the correctness of proportion used in cement mortor and various IS codes to determine the same?
what is the effect of duration of earth quake on framed structures ?
Define What is the best type of wood glue?
How do we determine the specific gravity of a cement?
satart to end steps by step process of building construction...? i want to planning theme accuretly
What are the different approaches in designing the floors of the service reservoirs?
how to identify the failure of building by expansive soils