Contrete reaches its full strength in 28 days. Then, why
are we removing shutter in 7/ 14 days?
Answer Posted / v.kapil
Concrete get its 50 % strength in 3 days and 66.6% in 7 days
with OPC grade of cement, we designed our structure for
full load including of factor of safety but actually such
loads never come structure in its whole life span, only 40-
50% loads ware accoured during construction so we can
remove our form work after 7-10 days but after confirmation
of cube results of 7 days.
| Is This Answer Correct ? | 15 Yes | 0 No |
Post New Answer View All Answers
what is idealized curve for concrere and steel
For making a new road in a village having a school & hospital , tell the steps of construction systemically ?
What is the substitute of Mastic Asphalt?
What is Critical path in Ms-Project ?
How much cement and water required for cement selery????
will fix foundation bolts at site with out template is there any procedure?
How to estimate the shuttering material requirement for a slab and beam and shear wall..? Please send thumbrule to estimate material required ( Plywood, Ms plates, runners, acrospans, jacks)
Design an underground tank of internal dimensions 6m x 3m x 3m. The soil surrounding the tank always remains dry. The tank shall be provided with a roof slab. The soil weighs 16000 N/m3 having an angle of repose of 30.
for G+2 residential building how much quantity of required in foundations,sub & superstructures per sq ft area
WAP to print 1) 1 1 1 1 1 1 1 1 1 1 2) 1 2 3 4 5 6 7 8 9 10
Pls help me to arrive the rates for centering shuttering for highbay using H-frames?
how to calculate number of bitumen for road asphalt
How to calculate the area of a irregular sized land in square feet?and what will be the total area of this land South-51.1ft , North-47.7ft , East-53.3ft , West-54ft ?please explain me how to calculate?
Is there any course for billing available in Mumbai? If yes then please mail me the details..
Dear sir, i want to NBCC & NTPC previous exam papers email Id : madhu_bingi@yahoo.co.in