calculation of cement bags in 1:2:4 concrete mix
Answers were Sorted based on User's Feedback
Answer / akashkhutia
For 1 m3 of concrete (1:2:4)
Required volume of concrete = 1 m3
Estimated volume of dry material = 1 x 1.65 = 1.65 m3
Mix totals = 1+2+4 = 7 (1:2:4 cement:sand:gravel)
Ingredient Volumes: 1.65 x 1/7 = 0.235 m3 cement
# Bags of cement: 0.235 m3 cement / .0332 m3 per 50 Kg bag
= 7 bags of cement
| Is This Answer Correct ? | 216 Yes | 82 No |
Answer / uma
For 1 m3 of concrete (1:2:4)
Metal -0.92cum
Sand -0.46cum
Cement-0.23cum
Weight of cement per cum-1440kgs
For 1:2:4 mix- 0.23x1440=331.2kgs
IN BAGS-331.2/50 =6.6Bags
| Is This Answer Correct ? | 86 Yes | 23 No |
Answer / balvinder bhagat
For 1 m3 of concrete (1:2:4)
Mix totals=7 (1:2:4 cement:sand:gravel)
Cement volume: 1* 1/7=0.143 m3 cement
#Bags of cement: 0.143 m3 cement * 1(As 1m3=6.4bag in 1:2:4)
=6.4 bags
| Is This Answer Correct ? | 89 Yes | 50 No |
Answer / anil raut
For 1 m3 of concrete (1:2:4)
for Required volume of concrete 1.00
Add extra for additional voids in concrete ( 25% to 35%)
0.35
Total qty= 1.35 Cum
Mix total (1+2+4) 7
Therefore Quantity of cement = (1.35/7) 0.19
Cum
Qty of Cement in bags = ( 0.19/0.03) 6.4 Bags say(7
bag)
Qty of sand in bags = ( 0.19*2) 0.39 Cum
Qty of Aggregate = ( 0.19*4) 0.77 Cum
| Is This Answer Correct ? | 39 Yes | 10 No |
Answer / vishnutom
For 1 m3 of concrete (1:2:4)
for Required volume of concrete 1.00
Add extra for additional voids in concrete ( 25% to 35%)=Say
35%=35/100=0.35.
Total qty=1+0.35=1.35 Cum
Mix total (1+2+4)=7
Therefore Quantity of cement = (1.35/7)=0.19 Cum
Qty of Cement in Kgs = (0.19*1440)=273.6Kgs
(1cum=1440Kgs)
Qty of Cement in bags= 273.6/50=5.4 bags=Say 6 bags
(50kgs=1 bag)
Qty of sand in bags = ( 0.19*2)=0.39Cum
Qty of Aggregate = ( 0.19*4)=0.77Cum
| Is This Answer Correct ? | 25 Yes | 11 No |
Answer / a
For finding cement
1+2+4=7
1/7x1.52
=.217x35.28
=7.65/1.25
=6.12bag/per 1cum.
| Is This Answer Correct ? | 46 Yes | 36 No |
Answer / suresh
for i m3 of concrete required
0.9 m3 of metal
0.45 m3 of mix
cement
0.45x1440/2x50 = 6.48kg
| Is This Answer Correct ? | 37 Yes | 28 No |
Answer / daniel dandan
for 1 cu.m of concrete, (1:2:4)
1=cement; 2=sand; 4=gravel
add 25% for loose volume(to cover voids),
total concrete volume = 1.25 cu.m.
total parts = 1+2+4 = 7 parts
cement = (1/7)*1.25
= 0.1786 cu.m
density of cement = 1440kg/cu.m
thus, 0.1786 * 1440 = 257.184kg.
for 40kg per bag of cement:
bag of cement = 257.14kg/(40kg per bag)
= 6.4 bags....answer
| Is This Answer Correct ? | 18 Yes | 9 No |
Answer / goran
mix Proportion =(1:2:4)
then (1C+2S+4G)=7C
for one cu.meter of concrete
concrete Gamma =2240 m3/kg
then
7C=2240=
C = 320 kg
for 50 kg bag
C = 6.4 bags per one cu.meter
| Is This Answer Correct ? | 11 Yes | 2 No |
Answer / s.mohamed imthiyaz
1+2+4=7........ then total ingredient=1.57
1part of cement..... So 1 / 7 =0.142
Then 0.142*1.57=0.2229
Unit weight of concrete is 1440kg/m3
0.2229*1440=320.97kg
1cement bag=50kg
320.97/50= 6.41 bags................
| Is This Answer Correct ? | 9 Yes | 3 No |
Pls help me to arrive the rates for centering shuttering for highbay using H-frames?
which grades of concrete is used in mega structures and well known structures? please name the structures and show their grade of concrete.
What is meant by Friction Pile?
What is the significance of cost estimate knowledge for an architect?
the size of one block is 390mm×190mm×190mm.then how much block will required for 4.6m × 3.4m wall.the thickness of wall is 190mm
10x10 slab design
what is the procedure of wet seiving. n percentage of silt in different type of soil?
technical name of shuttering plywood
1. why more stirrups are provided near the support? 2.where more stirrups is provided in a column and why? 3.why extra bars are provided at the top of beam? 4.what is the difference between overlap and lap lenght? 5.what is development lenght
what is meant by hidden beam & purpose of hidden beam
2 Answers Carwell Construction, NTDC,
what is mean by reestimation?
0 Answers Ste Infrastructure Pvt Ltd,
reinforcement lapping for short pile and long pile
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)