calculation of cement bags in 1:2:4 concrete mix
Answer Posted / daniel dandan
for 1 cu.m of concrete, (1:2:4)
1=cement; 2=sand; 4=gravel
add 25% for loose volume(to cover voids),
total concrete volume = 1.25 cu.m.
total parts = 1+2+4 = 7 parts
cement = (1/7)*1.25
= 0.1786 cu.m
density of cement = 1440kg/cu.m
thus, 0.1786 * 1440 = 257.184kg.
for 40kg per bag of cement:
bag of cement = 257.14kg/(40kg per bag)
= 6.4 bags....answer
Is This Answer Correct ? | 18 Yes | 9 No |
Post New Answer View All Answers
Cut Linten (RCC-1:2:4)on 10" wall - what should be the width and hight of cut Linten? Secondly, 1 X 1.6 foot,4" thick window sun/rain shed (Chajja)should consume steel,Cement, sand and Stone chips?
In the present situation of ban on mining sand from rivers,can we go for formation of earth dam filters viz;Horizantal sand blanket,inclined chimney and filters under rivetment with crushed rock sand of 6mm down size.If so what are the specifications and is there any codal provision for its authentication?
Formula for calculating the volume of bulb in underreamed pile
In foundation design, while we do the base pressure check, we normally check if the attained pressure value is less than the GROSS BEARING CAPACITY of the soil which is the sum of net bearing capacity of soil and the overburden pressure. Actually, the overburden pressure acts against the net bearing capacity of the soil and I feel that we are actually increasing the bearing capacity value and doing the check. I feel that this is NOT right. Please clarify on this.
can you give me the details of rate analysis of steel and concrete?
IS code for Rolling Margin of steel
what is the cost differene of a same structure when it is constructed with brick masonary, and when it is constructed with concrete as a frame structure.????????
1)Why we can use half brick in 4inch wall and 2)why not in 9+inch brick wall
If we have the center line of the Finnish road level and we want to know what level of pay would have offset the Lhs and Rhus RHS 1,2.5,5 1,2.5,5 m.
can any one give me sample question paper of BHEL at mdansari86@gmail.com as i m appearing for the same exam.
What are the RISKS during the project construction?
from where ican get sample papers for CET-delhi 2012
Laying bitumen concrete 40mm thick using 0.1372 cum of 13.2 10mm metal ,0.2387 cum of 10 5mm metal...what did it means please explain me how much cum of 10 mm metal need?
what is called Bulk Density of aggregate?
what discoveries did you have in relation to your course?