How to calculate the amount of cement & sand required for
plastering work with ratio 1:4 please give me an answer with
detailed step.
Answers were Sorted based on User's Feedback
Answer / rajarshi basu
Area to be plastered=100 m^2
Thickness of plaster=12mm=(12/1000)m= 0.012m
Volume of mortar required= 100 x 0.012= 1.20 m^3
Add 20% extra mortar for filling joint,depressions and
wastage.
Volume of the mortar= [0.20 X 1.20]+ 1.20=1.44 m^3
[Wet Volume]
Increase further by One-third of the volume to get Dry
volume
Quantity becomes= [(1/3) X 1.44]+ 1.44=1.92 m^3
Summation of proportion=1+4=5
For 12mm plastering in 1:4 cement :sand mortar mix:
1)Cement required= 1.92/5= 0.384 cu. m
No. of bags of cement= 0.384/0.0347=11.06 bags
>> 11 bags(say)
Cement used =11 x 50= 550 kg
2)Sand required= [1.92 x (4/5)]= 1.536 cu. m
Important note:
[Weight of 1 bag of cement= 50 kg
Cement should be always measured by weight to avoid
variation.
One 50 kg bag of cement weighs 1440 kg/cu. m
Volume of 1 bag of cement= 50/1440=0.0347 cu. m ]
Therefore to convert Cu. m into No of bags of 50 kg
cement,just divide the volume of cement by 0.0347
Hope u have understood!!!!
Is This Answer Correct ? | 482 Yes | 42 No |
Answer / shalini mishra
Area to be plastered=100 m^2
Thickness of plaster=12mm=(12/1000)m= 0.012m
Volume of mortar required= 100 x 0.012= 1.20 m^3
Add 20% extra mortar for filling joint,depressions and
wastage.
Volume of the mortar= [0.20 X 1.20]+ 1.20=1.44 m^3
[Wet Volume]
Increase further by One-third of the volume to get Dry
volume
Quantity becomes= [(1/3) X 1.44]+ 1.44=1.92 m^3
Summation of proportion=1+4=5
For 12mm plastering in 1:4 cement :sand mortar mix:
1)Cement required= 1.92/5= 0.384 cu. m
No. of bags of cement= 0.384/0.0347=11.06 bags
>> 11 bags(say)
Cement used =11 x 50= 550 kg
2)Sand required= [1.92 x (4/5)]= 1.536 cu. m
Important note:
[Weight of 1 bag of cement= 50 kg
Cement should be always measured by weight to avoid
variation.
One 50 kg bag of cement weighs 1440 kg/cu. m
Volume of 1 bag of cement= 50/1440=0.0347 cu. m ]
Therefore to convert Cu. m into No of bags of 50 kg
cement,just divide the volume of cement by 0.0347
Is This Answer Correct ? | 70 Yes | 9 No |
Answer / matrix civil & structural
THE METHOD GIVEN BY Mr.BASU IS SEEMS TO BE APPROPRIATE TO ESTIMATE THE QUANTITY OF CEMENT AND SAND IN PLASTERING.
Is This Answer Correct ? | 66 Yes | 21 No |
Answer / baldeo m. sarwe
Yes this formula is near abovet is correct
Is This Answer Correct ? | 27 Yes | 10 No |
Answer / xxx
this answer is write but their is not mention that weight of sand...
Is This Answer Correct ? | 4 Yes | 4 No |
Answer / kanheya lal
footing by structures weight formula in steel dia for load
Is This Answer Correct ? | 1 Yes | 1 No |
Can any body help me out by telling hoe swelling pressure test of soil is carried out ? some body told me the procedure & formula (change in length /116.3*100%) but still i am confused ? pls help.
how 2 find out slap steel quantity ? plz help me
if in column reinforcement lower dia connect to higher dia then from wher we want to start higher dia steel
How to do base isolation using ETABS software?
DEFINATION OF CIVIL ENGINEERING
How many BRICKS required for 10 cumic of brickwork
what is BPM in concrete demolition hammers. what is better a higher value or lower
How much steel and concrit required in 1000 square feet slab?
how preparing for barbending schedule ? how to preparig for two leged stirrups?
how should i calculate the concrete volume in a circular RCC wall ? what is the formula pls add diagram link for explaing
What is the Unit weight of coarse sand (F.M- 2.20) ?????
Define What is an ice dam sock?