how to find the carpenter work per day? how many cubic feet
they should be work per day?

Answers were Sorted based on User's Feedback



how to find the carpenter work per day? how many cubic feet they should be work per day?..

Answer / girish rawat

ON AN AVERAGE 1 CARPENTER I SEMI SKILLED CARPENTER AND 1
HELPER WITH GIVE YOU AN OUTPUT OF 10 TO 12 M2 OF SHUTTERING.
IT DECREASES IF YOU ARE FIXING BEAM BOTTOM OR STEP FOOTING.
IT INCREASES DURING COLUMN FIXING AND SLAB DECK SHUTTERING.

Is This Answer Correct ?    45 Yes 3 No

how to find the carpenter work per day? how many cubic feet they should be work per day?..

Answer / nagu

1 carpenter 2 helper 4 to 6m2 per day so 8hours

Is This Answer Correct ?    3 Yes 1 No

how to find the carpenter work per day? how many cubic feet they should be work per day?..

Answer / md.sami

door,window work comes under furniture carpenter, if you ask wooden carpenter no will get you

Is This Answer Correct ?    1 Yes 0 No

how to find the carpenter work per day? how many cubic feet they should be work per day?..

Answer / geethu

i hav asked about wood carpenter output?(doors,windows)

Is This Answer Correct ?    0 Yes 3 No

how to find the carpenter work per day? how many cubic feet they should be work per day?..

Answer / harish

average one carpenter one helper they give out put of 12-
14m2of shuutering

Is This Answer Correct ?    4 Yes 10 No

Post New Answer

More Civil Engineering Interview Questions

sir, whitch is the best book (writer name) for prepration of gate....

1 Answers  


What is the difference between NP2 and NP3 Class RCC Hume Pipes

5 Answers   Honest Derivatives Pvt. Ltd, Indian Hume Pipe Co, M2K,


what is the cost of per cum of pile foundation?

1 Answers  


Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quantity of concrete by explaining all formulas involved.

19 Answers   DNA Infrastructure, HCC, L&T,


how we calculate the grade of the Bituminous materials.?????

1 Answers   FES,


how many kg of gypsum required for 100 sq.ft wall (thk of plaster is 12 mm)

1 Answers   Indu Projects, Tata Tiscon,


How to convert 20 dia bar to 16 dia bar in beam without reducing the steel weight

1 Answers   L&T,


cement consumption per square feet in multi storeyed building

9 Answers   Dhar Associates,


what is the pile

1 Answers   Chandra Group, GVR Constructions, Simplex,


how much L is provide in footings. what is min and max length of L. what is the formula

1 Answers  


how to check the quality of sand?

5 Answers   L&T,


please give me the rates of RCC(CUM), PCC(CUM), Brick Work(CUM), Tile Flooring, Saria Shuttering

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4453)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)