for construction of 1 cum of brickwork what is requirement of cement, sand and bricks

Answers were Sorted based on User's Feedback



for construction of 1 cum of brickwork what is requirement of cement, sand and bricks..

Answer / ravi

bricks 500
volume of mortar =0.2035 m3
dry volume of mortar =1.33*.2035=.306 m3
cement =.306*1/7=.0403 m3
sand=.306*6/7=.362 m3

Is This Answer Correct ?    3 Yes 0 No

for construction of 1 cum of brickwork what is requirement of cement, sand and bricks..

Answer / nilesh jain

525 bricks ( with wastage ),1.35 bags of cement, 0.27 cum sand.

Is This Answer Correct ?    1 Yes 2 No

for construction of 1 cum of brickwork what is requirement of cement, sand and bricks..

Answer / ari kumar

500 bricks,20cft sand,66kg cement

Is This Answer Correct ?    1 Yes 7 No

Post New Answer

More Civil Engineering Interview Questions

can i get placement in 2nd or 3rd year in college..

2 Answers  


grade of cement used for plastering? why?

4 Answers   Green Valley Shelters (P) Ltd, NCCL,


qube strenth in 7nth days test

11 Answers   IVRCL,


Pls provide me with the calculation or codes related to de- shuttering of flat slabs

2 Answers  


How to calculate water cement ratio in mix desion

2 Answers   Delta,






Why are steel plates inserted inside bearings in elastomeric bearing?

0 Answers   Bechtel,


difference between nominal mix and design mix difference between nominal size and actual size of brick,aggregate etc

1 Answers   L&T,


# 1. Size of slit content in sand. # 2. Gravity of sand # 3. Water observation capacity of sand. # 4. minimum crushing Strength of sand.

1 Answers   Brigade,


Please tell me the quantity of cement, sand, flyash, foaming agent required for 1 cubic meter of cellular lightweight concrete blocks. also , is there any admixtures required for the CLC blocks production.

0 Answers  


I would like to get the formula How can i calculate the productivity of a mason in terms of brick laying and plaster. i have 6000 Sqmt of interlock laying work i want to calculate - how many masons required to do the job - in how many days can it be done - what will be the production rate in 8 hours shift/ per mason if i can get some excell sheet , it will really help me in my calculations

0 Answers  


cause of cylinder test failure

0 Answers  


Why we do design mix of concrete when there is nominal method using the IS-Code available ?

14 Answers   Engineers India Limited,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)