Trapezoidal section footing calculation of Volume & its Area

Answers were Sorted based on User's Feedback



Trapezoidal section footing calculation of Volume & its Area..

Answer / sandeep

V=(L X B X d) + h/6(A1 + A2 + 4Am)

L=Length of footing
B=Breadth of footing
d=Depth of bottom portion
h=Height of trapizodial portion (D-d)
A1= Area of bottom portion (L X B)
A2= Area of top portion (l X b )
Am= Mean area of A1 AND A2

Is This Answer Correct ?    42 Yes 5 No

Trapezoidal section footing calculation of Volume & its Area..

Answer / chandramouli bv

V=(L X B X d) + h/3(A1 + A2 + SQRT(A1 X A2 )

L=Length of footing
B=Breadth of footing
d=Depth of bottom portion
h=Height of trapizodial portion (D-d)
A1= Area of bottom portion (L X B)
A2= Area of top portion (l X b )

Is This Answer Correct ?    37 Yes 5 No

Trapezoidal section footing calculation of Volume & its Area..

Answer / anand nair

H/3 (A1 + A2 + sqrt A1A2)

Is This Answer Correct ?    22 Yes 1 No

Trapezoidal section footing calculation of Volume & its Area..

Answer / sathish

(LxBxD)+((h/3)x((A1+A2)+(sqrt of (A1xA2))))

Is This Answer Correct ?    13 Yes 2 No

Trapezoidal section footing calculation of Volume & its Area..

Answer / ilayaraja

V=(L X B X d) + h/3(A1 + A2 + SQRT(A1 X A2 )

Is This Answer Correct ?    4 Yes 2 No

Trapezoidal section footing calculation of Volume & its Area..

Answer / waqas

(A1 +B1)/2

Is This Answer Correct ?    2 Yes 4 No

Trapezoidal section footing calculation of Volume & its Area..

Answer / k.sankar

(L*b)+(h/3(a1+a2)+sqroot(a1*a2)

Is This Answer Correct ?    3 Yes 9 No

Trapezoidal section footing calculation of Volume & its Area..

Answer / sweety

((L+B)D+h/3)(A1+A2+root of(A1+A2))

Is This Answer Correct ?    5 Yes 14 No

Post New Answer

More Civil Engineering Interview Questions

Can any colleague send me the steel frame pictures of roofs, beams, columns, footings, roof bends, door bends etc. I shall be very gratefull.Suhail_akhter@hotmail.com

0 Answers  


proportions of m10, m15, m20, m25, m30, m40, m45, m50, m60, m70, m75, m80 etc

12 Answers   L&T,


In case of a beam ,main steel is provided along the longer span because, bending moment is directly proportional to length but why in case of one way slab main steel is provided along shorter span while as bending takes place along longer span?comment

8 Answers   Power Grid,


how to identify np3 pipe and np4 pipe

0 Answers   NCC, Petron ltd, RCC Laboratories India Private Limited,


i m a btech 1st year student of civil branch. i want to do mba in future after having some work experience in civil field.is there any mba course made exclusively for civil engineers?

3 Answers  






Explain what is change order request?

0 Answers  


What is meaning of tlc

0 Answers   Backbone,


How to calculate quantity of binding wire for any kind of structures. How to calculate quantity of nails in 1 sq m shuttering.

2 Answers   Vodafone,


how many brick sand cement require (1:5) 1 cum

4 Answers   L&T,


Civil engineering related

0 Answers   HSS, Jaypee,


What is Gabion Walls?

1 Answers   Rajhans Infracon,


cavitations is caused by

2 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)