Cube tests of concrete are failed at 7 days and 28
days.What is your next action?
Answer Posted / nravindran
Go for NDTest, if it is not satisfied go for Core test that
is also failed go for concrete strengthing process As per
structural consultant comments
| Is This Answer Correct ? | 19 Yes | 4 No |
Post New Answer View All Answers
reinforcement slab, beam and column formulas?
What is the release of lien?
how to calculate Rate of analysis for 100 m3 Any ratio of concrete ? including labour
How much permissible bearing capacity requires for open footings(isolated) and what type pile foundatuon prefering for coastal areas?
WHERE CAN I GET THE PREVIOUS QUESTION PAPERS OF APGENCO FOR THE THE POST OF Tr.ASSISTANT ENGINEER(CIVIL)
What is labor and material payment bond?
WHAT R THE GENERAL TECH QUESTIONS ASKED FOR THE INTERVIEW FOR AN AUTOMOBILE INDUSTRY,SPECIALLY DESIGN DEPT
Define What is the origin of name Railway Sleepers?
how many sqft or cft of work done by a mason per day in all works such as brick,block,concrete,shuttering carpenter,reinforcement fabricator,painter,door window carpenter.....everything thank you
what is the minimum cement content for M20 & M25 as per is code -456(2000).
from one meter cube of stone masonry structure how much cubic meter of cement mortar we use as our estimation 25-30% is that correct for estimation of quantity of sand and cement(2:1) proportion of mortar
What are the advantages of building a dam on the river nile?
What is the unit standard weight,thicknessof C.I>Pipe of various Dia upto200 MM(as per IS1538)
What are the phases inspections are done by local authority while construction?
what is tension column?