Cube tests of concrete are failed at 7 days and 28
days.What is your next action?
Answer Posted / prabhakara rao.b
Go for NDT If it is not satisfied go for Core test that
is also failed go for there possibale demolisan that coloum
it is not possible we go for Restrengthing.
| Is This Answer Correct ? | 4 Yes | 3 No |
Post New Answer View All Answers
What are the responsibilities of a site manager?
Explain what are the skills required to become an architect?
Are cruise ships built for the transatlantic run?
Explain the different types of roofing systems?
What is the cost of formwork for columns/beams/rcc walls also what is the cost of shuttering for roof slab at height of 25 feet
Define What is the force exerted by the Tacoma narrows bridge?
How to fix toll charge for a particular vehicle at toll booths in a highway?
As in practice, we are deducting every 2d for 90 degree bend but from where it comes means derivation or reference of IS Code.
may i know the detailed description of cutting length
Doul Bar reinforcement and details of drawing.
design the irrigation canal(b,B,h )head is 3tms of water is supplied to the 200hectars of area and the base period crop is 150days dance to water travels as 35km.the canal section is trapezoidal and also calculate the slop the canal
What is the difference between built area and super built up area?
Can we apply curing compound on ceiling (slab Bottom)
Wat is meant by Aecron brick?
What is packing Factor ?