how to calculate sand, cement quantity for plastering (1:5)? what"s the formula?
Answers were Sorted based on User's Feedback
Answer / rajarshi basu
Let Area to be plastered=100 m^2
& Thickness of plaster= 12mm=(12/1000)m= 0.012m
Volume of mortar required= 100 x 0.012= 1.20 m^3
Add 20% extra mortar for filling joint,depressions and
wastage.
Volume of the mortar= [0.20 X 1.20]+ 1.20=1.44 m^3
[Wet Volume]
Increase further by One-third of the volume to get Dry
volume
Quantity becomes= [(1/3) X 1.44]+ 1.44=1.92 m^3
Summation of proportion=1+5=6
For 12mm plastering in 1:5 cement:sand mortar mix,
1)Cement required= 1.92/6= 0.32 cu. m
No. of bags of cement= 0.320/0.0347=9.22 bags
>>9 bags(say)
Kgs of cement required=9 x 50= 450 kg (approx)
2)Sand required= [1.92 x (5/6)]= 1.60 cu. m
[Weight of 1 bag of cement= 50 kg
Cement should be always measured by weight to avoid
variation.
One 50 kg bag of cement weighs 1440 kg/cu. m
Volume of 1 bag of cement= 50/1440=0.0347 cu. m ]
Therefore to convert Cu. m into No of bags of 50 kg
cement,just divide the volume of cement by 0.0347
| Is This Answer Correct ? | 269 Yes | 26 No |
Answer / sandeep tv
let Area to be plastered=100 m^2
& Thickness of plaster= 12mm=(12/1000)m= 0.012m
Volume of mortar required= 100 x 0.012= 1.20 m^3
Add 20% extra mortar for filling joint,depressions and
wastage.
Volume of the mortar= [0.20 X 1.20]+ 1.20=1.44 m^3
[Wet Volume]
Increase further by One-third of the volume to get Dry
volume
Quantity becomes= [(1/3) X 1.44]+ 1.44=1.92 m^3
Summation of proportion=1+5=6
For 12mm plastering in 1:5 cement:sand mortar mix,
1)Cement required= 1.92/6= 0.32 cu. m
No. of bags of cement= 0.320/0.0347=9.22 bags
>>9 bags(say)
Kgs of cement required=9 x 50= 450 kg (approx)
2)Sand required= [1.92 x (5/6)]= 1.60 cu. m
[Weight of 1 bag of cement= 50 kg
Cement should be always measured by weight to avoid
variation.
One 50 kg bag of cement weighs 1440 kg/cu. m
Volume of 1 bag of cement= 50/1440=0.0347 cu. m ]
Therefore to convert Cu. m into No of bags of 50 kg
cement,just divide the volume of cement by 0.0347
| Is This Answer Correct ? | 60 Yes | 12 No |
Answer / ashwin
cement:sand= 1:5
for 1cum= 1/6
=0.166
so cement for 1 cum=0.166cum
but volume of 1 cement bag is=.033cum
bag required per cum is=.166/.033
=5 bags
sand required is=0.166*5
=0.833 cum
| Is This Answer Correct ? | 100 Yes | 58 No |
Answer / yogesh khandelwal
Let Area to be plastered=100 m^2
& Thickness of plaster= 12mm=(12/1000)m= 0.012m
Volume of mortar required= 100 x 0.012= 1.20 m^3
Add 20% extra mortar for filling joint,depressions and
wastage.
Volume of the mortar= [0.20 X 1.20]+ 1.20=1.44 m^3
[Wet Volume]
Increase further by One-third of the volume to get Dry
volume
Quantity becomes= [(1/3) X 1.44]+ 1.44=1.92 m^3
Summation of proportion=1+5=6
For 12mm plastering in 1:5 cement:sand mortar mix,
1)Cement required= 1.92/6= 0.32 cu. m
No. of bags of cement= 0.320/0.0347=9.22 bags
>>9 bags(say)
Kgs of cement required=9 x 50= 450 kg (approx)
2)Sand required= [1.92 x (5/6)]= 1.60 cu. m
[Weight of 1 bag of cement= 50 kg
Cement should be always measured by weight to avoid
variation.
One 50 kg bag of cement weighs 1440 kg/cu. m
Volume of 1 bag of cement= 50/1440=0.0347 cu. m ]
Therefore to convert Cu. m into No of bags of 50 kg
cement,just divide the volume of cement by 0.0347
| Is This Answer Correct ? | 13 Yes | 4 No |
why should we have to take 20% of wet mortar & 1/3rd of Dry mortar......is there eny code for that...or plz tell me where it coms from......plz clear me ....
| Is This Answer Correct ? | 12 Yes | 3 No |
Answer / adz
1:5 proportion for (1)cement @ 40kg): (5)sand @ 33 kg(S.G
@2.6) gives you approximate volume of 0.142 cubic meter.
if you want exact volume, provide the specific gravity of
your materials and include air content and water for your
volume...
| Is This Answer Correct ? | 8 Yes | 0 No |
Answer / abrar
c:m ratio for plastering (1:5) for 1 cum
sand 1cum = 1.25cum .... constant in all ratios
cement 1cum = 1.25 x 1440
------------ = 360 kgs = 7.2 bags
5
| Is This Answer Correct ? | 16 Yes | 12 No |
what is steel consumption for high rise building column, beam, slab,footing
Why Vitrified tile are getting pop up.
what is difference between NP2 NP3 NP4 CONCRETE HUME PIPES USED AT SITE
what is fe 415 steel
15 Answers L&T, Nabard, Rahul Computers,
i want to know the easy way to find the quantity of steel in a slab , coloumn
What is the dimension of Slump cone which is used to measure the Slump value of concrete? Slump value for Pile concrete? Slab concrete? Column concrete?
how gradation of aggregates effect on slump of fresh concrete?
how much cement and sand consuptin in 4 inch siporex walls 100 sq ft
how much brick, cement, and sand required in 1mtr X 0.23mtr X 1mtr brickwork(1:4), 230mm thick wall and 10mm thick mortar , brick size 230mm X 70mm X 110mm
How high should the water tank be to provide a 60 psi at base of this water tower?
What is meant by Crystal Concrete?
Can anybody tell me how to calculate the quantity of a trapezoidal footing?With its formula and an example.
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)