Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


what is the procedure of plastering..?

Answers were Sorted based on User's Feedback



what is the procedure of plastering..?..

Answer / k.l.b.srinivas

BEFORE STARTING PLASTERING WORK IF ANY CONCRETE ELEMENTS
LIKE COLUMNS,WALLS ETC. WE HAVE TO DO POINTING / HACKING.
ALL THE SURFACES WHERE PLASTERING IS TO BE DONE SHOULD BE
WET BY APPLYING WATER. AT THE JOINTS GROOVES SHOULD BE
MAINTAINED TO AVOID CRACKS. PROPORTION OF MIXING SHOULD BE
PROPER.

Is This Answer Correct ?    4 Yes 0 No

what is the procedure of plastering..?..

Answer / samyak jain

The Process of plastering is that Throw 1 trovel filled with
material on to the wall must me at the distance of 20 to 30
cm far from the wall so that each n every particle get
bounded/sticked with the wall. And the trovel must be
partialy filled with mortar.

Is This Answer Correct ?    3 Yes 2 No

what is the procedure of plastering..?..

Answer / sjtbehera

follow the civil book or ask any mistri

Is This Answer Correct ?    3 Yes 6 No

Post New Answer

More Civil Engineering Interview Questions

Q1) I am having an interview in a construction company for a large sewage project . Since I have not done any such project , there are some queries from my end. Pls. help me to solve them. I will be thankful to you :- a) Normally for large project 400-600 houses & around 1600 peoples , how much dia pipe is used and which type of pipe is used? b) For trenching , I have heard that IS 1200 implies, what are the rules of calculating earthwork in case of depth of 2m or above ? c) To prevent soil to fall when depth of trench is more , what steps are taken and how there qty. is calculated . Like I have heard about timbering . what is this ? d) What are the rules for disposing off the excavated soil ? e) How the pipes that are used are being jointed? f) In case of cleaning on choks , is there any intermediate things provided? g) For foul gases any outlets are provided thru out length of pipeline? h) What is the flow digram like from houses thru small pipe to main pipeline than where main pipeline disposes wastage ? i) Any other thing that has to be kept in mind while calculating earth work for excavation like steps are made and other things? How earthwork is calculated in case of steps ? Pls. explain with a sketch. Regards,

1 Answers  


If we buy crush sand for 3200/ Brass and cement for Rs350 /Bag and flyash 1200 / tonne....and my production is 230 Bricks per bag than how much cost is required for 1 flyash brick?

0 Answers   ABC,


16 questions out of 55 were from the book GUPTA N GUPTA OBJECTIVE of civil engineering. Total ques were 4 ques from hydraullics, 7 from BMC, 4 FROM SOM, 4 from soil mechanics, 6 from transportation, 5 from engineering drawing.

0 Answers  


What is the requirement for over all CG of DG from the foundation surface to absorb the vibration of heavy set.

0 Answers  


What is OSHA compliance?

0 Answers  


How can find weight fosmula in kg/m for circular cylinde steel bar?

6 Answers  


What will be the exam pattern and syllabus for j.e post of haryana staff selection commision? Advt no. (02/2015) Some people says it would only be objective type question papers while others say it would be same as ssc (1 objective,1 conventional) ?? Please answer this question it is needfull to all.

0 Answers   HSSC,


What is bending moment

2 Answers   Skyline Builders,


What is the name of this multiplication factors ?

0 Answers   Engineers India Limited, L&T,


what is mean by quality in terms of construction

2 Answers  


how to calculate quantity of concrete volume of pile with bulb  

1 Answers  


Can inverted beams used in pipes during construction?

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)