how to calculate sand, cement quantity for plastering (1:5)? what"s the formula?
Answer Posted / rajarshi basu
Let Area to be plastered=100 m^2
& Thickness of plaster= 12mm=(12/1000)m= 0.012m
Volume of mortar required= 100 x 0.012= 1.20 m^3
Add 20% extra mortar for filling joint,depressions and
wastage.
Volume of the mortar= [0.20 X 1.20]+ 1.20=1.44 m^3
[Wet Volume]
Increase further by One-third of the volume to get Dry
volume
Quantity becomes= [(1/3) X 1.44]+ 1.44=1.92 m^3
Summation of proportion=1+5=6
For 12mm plastering in 1:5 cement:sand mortar mix,
1)Cement required= 1.92/6= 0.32 cu. m
No. of bags of cement= 0.320/0.0347=9.22 bags
>>9 bags(say)
Kgs of cement required=9 x 50= 450 kg (approx)
2)Sand required= [1.92 x (5/6)]= 1.60 cu. m
[Weight of 1 bag of cement= 50 kg
Cement should be always measured by weight to avoid
variation.
One 50 kg bag of cement weighs 1440 kg/cu. m
Volume of 1 bag of cement= 50/1440=0.0347 cu. m ]
Therefore to convert Cu. m into No of bags of 50 kg
cement,just divide the volume of cement by 0.0347
Is This Answer Correct ? | 269 Yes | 26 No |
Post New Answer View All Answers
in the construction of residential building what type of tank are used?where?why & what is its purpose?
how ratio is calculated for any grade of concrete. for e.g. sppose M20 requires(x;y:z) quantity of cememt sand and aggregate.
What is a bearing capacity of soil?
pls mail some more tecnical qustions at msaranya2610@gmail.com
What difference comes in constructing of house and a housing complex like society
What is the strength of cement?
What are the benefits of rcc pipes over steel designed pipes?
How much cements bag (or in KG) required for 1 Sq. M concrete, for M-30 grad concrete as per CPWD and where is thr proof on site
RR masonry rate analysis
I need old MMUP exam question and answer for Civil engineering
what isload waring calculation
57. Calculate the volume of a truck loaded with stone chips whose data are as follows– 5 Top Length - 13-9, 13-10, 13-09 Bottom Length - 13-11, 13-10.5, 13-10 Top width - 8-7.5, 8-8, 8-7 Bottom width - 8-7, 8-8, 8-7.5 Depth - 2-0, 1-11.5, 1-10, 1-11, 1 -10.5, 1-11.75, 1-11
what is mean by reestimation?
what is thumb rule for calculating the size of ISMB required for a particular length of span
how can we calculate steel value, depending on load