how to calculate sand, cement quantity for plastering (1:5)? what"s the formula?
Answer Posted / ashwin
cement:sand= 1:5
for 1cum= 1/6
=0.166
so cement for 1 cum=0.166cum
but volume of 1 cement bag is=.033cum
bag required per cum is=.166/.033
=5 bags
sand required is=0.166*5
=0.833 cum
Is This Answer Correct ? | 100 Yes | 58 No |
Post New Answer View All Answers
will fix foundation bolts at site with out template is there any procedure?
Why are pull-out tests performed for soil nails?
Dear Sir What is the Contraction joint for base Slab
Can we use Polystyrene as a Bitumen modifier !! if so is it a good MS research topic ? and what type of laboratory tests will be conducted during Research work ??
What is the primary difference between adsorption and absorption?
Analyze the rate for 1st class brick work in superstructure with 1:6 cement sand mortar. Consider 1000 cu.ft quantity and work out the rate per cu.ft
what is conventional shuttering rate per square feet of built up area? what is Mivan shuttering rate per square feet of built up area? what is coupler shuttering rate per square feet of built up area?
01. a. Diagram of a slump cone…………… 1 b. Size of Slump Cone…………… 1 c. Volume of a slump cone by av. Dia method…………… 1 d. Volume of a slump cone by av. area method…………… 1 e. Volume of a slump cone by frustrum method …………… 1 f. Angles of slump cone …………… 1 g. Slump measured by slump cone due to…………… 1 h. Slump does not measured by cylinder / cube due to …………… 1 i) ii) i. Slump cone is to be filled in……………………..Layers.
door and window wood work calculations and different methods
How to calculate woden area in sft and Cft
What is Critical path in Ms-Project ?
by which materials we can prepare circular shuttering with tentative cost of material(rate analysis)
hai, kindly send anyone for output workers format details for construction project in foundation to finishing.
What is meant by engineering drawing?
step by step procedure to find out the percentage of steel in coloum,beam,slab,footing in detailed