Answer / shanmugam
m7.5 = 1:5:10
m10 = 1:4:8
m15 = 1:3:6
m20 = 1:2:4
m25 = 1:1.5:3
m30 = 1:1:2
i think there is a ratio for m35= 1:1:1
and after that only the mix design starts........
| Is This Answer Correct ? | 12 Yes | 88 No |
what is the difference between red bricks& cement bricks
sir, please send me the web address of chennai railway to know the online examresults of junior engineer[civil].
how can economic during construction of a project.
what is column foundation
What is the difference between BC and SDBC
Required amount of Steel bars, cement/ square feet for roofing of residential building upto 3rd floor.
Differentiate first angle & third angle projection?
how to calculate the amount of cement & sand required for plastering
Formula of area of crane hook
For G+4 storied building having 76000 sft per each floor, can you prepare schedule in such a way that structure should be completed with in 41/2 months and finishing be completed with in 51/2 months?
how to calculate quantity of bricks in circular manhole with examples.
what is the stripping time of beam column & slab?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)