Answer / jayaraaj

1 bag of Cement Contains 50Kg
in 1 cum required cemnt is 1440kg
since,Volume of one Cement bag = 50/1440 = 0.035m3
:1 bag = 0.035m3 volume

Is This Answer Correct ?    19 Yes 4 No

how much the volume of one packet cement ?..

Answer / hema morampudi

1 bag of Cement Contains 50Kg
If Freshly packed cement bag the standard density is 94
lbs/ft3 (1505 kg/m3)
Volume of one Cement bag = 50/1505 = 0.0332m3
:1 bag = 0.0332m3 volume

Is This Answer Correct ?    18 Yes 9 No

how much the volume of one packet cement ?..

Answer / muthaa

1.25 cft

Is This Answer Correct ?    5 Yes 1 No

how much the volume of one packet cement ?..

Answer / mughal

50/1440 =0.0347cu.m

Is This Answer Correct ?    0 Yes 0 No

how much the volume of one packet cement ?..

Answer / suresh bariya

1 bag of cement = 50 Kg
1 bag of cement = 35 Liters
1 bag of cement = 1.25 Cft
1 bag of cement = 0.0347 Cum

Is This Answer Correct ?    0 Yes 0 No

how much the volume of one packet cement ?..

Answer / akram

50 kg

Is This Answer Correct ?    0 Yes 1 No

Post New Answer

More Civil Engineering Interview Questions

where do Tie beams used in foundations?

1 Answers   Architects,


providing, fixing, removal of pockets of size 100*150*300mm to 500*600*1000mm for foundation. the shuttering material used for making &fixing of pockets shall be removed by the contractor without damaged to pockets. if any damage occurred, the same shall be rectified by the contractor is to handover the pockets to forge shop engineer with proper marking of centre lines, levels etc.

1 Answers  


What is the minimum size of the particles of silt soil?

1 Answers  


Providing and fixing in position Tor steel to footings, foundation, slabs, beams, columns, canopies, stair case, newels, chajjas, lintels, etc. including cutting, bending, hooking the bars, binding with wires. give me the rate M.ton.

1 Answers  


WHAT IS THE IMPORTANCE OF FLY ASH BRICK?

2 Answers  


what are the challenges of being a team leader and a supervisor?

1 Answers  


What is Time at Large?

1 Answers  


Define polar co ordinates.

1 Answers  


How can we compact the soil on slope portion? What is the Grade II of Stone Metal?What type tests carried out on BBM road?

1 Answers  


which grade of steel is better for construction of building under earthquake zones ? why?

2 Answers   Noah Solutions,


how to calculate no. of bricks for 1 cft? how to calculate cement and sand in cft?

13 Answers   L&T,


What is a MIS report?

1 Answers   NCC,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4453)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)