How to Determine the Quantity of Cement Sand , Aggregete
and Reinforcement Bars in 30 feet X 40 Feet and Height is 4
Feet .
Answer / prabu
1 feet = 0.3048 meter
30'*40'*4' = 9.144 *12.192 * 1.2192 meter
total volume = 135.92 meter cubic
1 bag cement = 50 kgs
unit wt of cement = 1440 kg/m3
density = weight/volume = 50/1440 = 0.0347m3
if concrete grade is M20 and ratio is 1:1:2
1+1+2 = 4
cement = 135.92/4 = 33.98
33.98/0.0347 = 979.25 bags
1 cement bag = 50 kgs, so
979.25 bag = 979.25 * 50 = 48962.53 kgs
sand = 1* 33.98 = 33.98 m3
aggregate = 2*33.98 = 67.96 m3
for slab = 0.7 -1% of concrete volume (reinforcement provided )
for beam = 1 - 3%
for column = 1 - 5 %
for footing = 0.8 - 8%
in this problem = 135.92 m3 concrete
for slab = 135.92 * 0.007 = 0.95m3 volume reinforcement provided.
ans =
cement = 48962.53 kgs or 979.25 bags
sand = 33.98 m3
aggregate = 67.96 m3
for slab = 0.95m3 volume reinforcement provide
Is This Answer Correct ? | 9 Yes | 5 No |
resins are not soluble in water soluble in spirit used in varnish left behind on evoporation of oil
give me the mix proportion for design mix concrete M10 grade 1:4:8
13 Answers Gammon, IOCL, PSL, SDG, Simplee, STUP Consultants Pvt Ltd,
Onsite percentage wastage of Concrete, Rebar, Blockwork/Brickwork, Plaster, Floor tiles ??
how to calculate concrete qty for footing using M25 grade 1:1:2 for 731 cft.
9 Answers Abuilding Lab, L&T, MPSC, Vellapally,
what is hook's law
where cross hairs in surveying telescope are fitted
What are the different types of piles?
i have open space in my house, i want to make pcc there, si want to know how i calculate material , my area measurement is 10' x 10' x .25', pls tell me how much need cement, sand, concrete,if possible u than pls tell me the formula
1) is maximum size of aggregate ristricted to 20 mm for M- 50 grade concrete? If yess or no code the authority?
If in a structure, e.g, 20mm steel bar is not available and we use 16mm steel bar instead of 20mm bar, how can we calculate the no. of steel bars for 16mm diameter bar?
how to calculate concrete pouring of foundation
How do we say The LAP LENGHT is 50D to 60D ?????