Answer / m.s.sathyajeth raja
M10-1:3:6
M15-1:2:4
M20-1:1.5:3
M25-1:1:2
From M30 Onwards the design mix should be adopted at the Site....since it is a Major form of Concrete
Is This Answer Correct ? | 83 Yes | 11 No |
Answer / kondala rao pilli
FOR M25 THE MIX IS 1:1:2,FOR THE REMAINING ARE DESIGN MIXES
Is This Answer Correct ? | 51 Yes | 21 No |
Answer / er.yogesh yadav
m-25 1:1:2
all other
concrete grade
its desgin mix
and depend to
structre.after
that desgin it.
Is This Answer Correct ? | 12 Yes | 2 No |
Answer / xyz
In Books the ans of M25 is 1:1:2 But it is in olden day's
ratio when 53 grade cement is not available, Now to make
concrete mix you have to design the design mix.
Is This Answer Correct ? | 8 Yes | 7 No |
Answer / kamran khan
M5 = 1:4:8
M10= 1:3:6
M15= 1:2:4
M20= 1:1.5:3
M25= 1:1:2
M30= 1:1:1
M35= 1: 0.75.1
There are m= mix and 5.10.15...........compressive strength.......
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / sobhan kuumar
M5 = 1:5:10
M7.5 = 1:4:8
M10 = 1:3:6
M15 = 1:2:4
M20 = 1:1.5:3
M25 = 1:1:2
M30 = 1:1:1
Is This Answer Correct ? | 2 Yes | 2 No |
Answer / suman roy/amrita kr biswas
M5-1:5:10
M10-1:3:6
M15-1:2:4
M20-1:1.5:3
M25-1:1:2
M30-1:1:1
M35-1:0.75:1
ABOVE ARE BASED ON DESIGN MIX
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / abhishek raj
whatever the grade of the concrete is the design mix or the
components of mix depends upon us.,it mean it all be decided
at on the site and the structure which is going to be casted
at that time.
Is This Answer Correct ? | 2 Yes | 7 No |
Answer / praveenpalaparthi
M25:1:1:2
M30:1:1:2
M35:1:0.75:1
M40:1:0.5:0.5
Is This Answer Correct ? | 10 Yes | 24 No |
What is progress payment?
1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement Required? Brick Size 9" 4.5" 3"
48 Answers Alcove Infrastructure, Anantha Infra, L&T, Microqual, Shoba Devlopers, SSC, UltraTech, Valdan, VVA Developers,
WAS PUMP MODEL WXB DESIGNEDIN ACCORDING API 610 STANDARD?
If we buy crush sand for 3200/ Brass and cement for Rs350 /Bag and flyash 1200 / tonne....and my production is 230 Bricks per bag than how much cost is required for 1 flyash brick?
Rate analysis of 150mm, 100mm, & 230mm thk BBM work
what is steel consumption for high rise building column, beam, slab,footing
what is the ratio of steel and concrete to use in slabs , beams, columns ?
in the construction of building,we are use formula for laping? such that how many formulae we use? which are them?
what is a weight of 10mm, 20mm, 40mm aggregate ?
7500 liters capacity of water tank find the inner Length L = ? Breadth B = ? Depth D = ? in feet
Whta is the proportion of M30
which software is better for design and analysis of buildings (stadd pro ) or (Etabs)