Answer / sumanthteja

Bridge scour is the removal of sediment such as sand and
rocks from around bridge abutments or piers. Scour, caused
by swiftly moving water, can scoop out scour holes,
compromising the integrity of a structure.

Bridge scour is one of the three main causes of bridge
failure (the others being collision and overloading). It has
been estimated that 60% of all bridge failures result from
scour and other hydraulic-related causes

Is This Answer Correct ?    1 Yes 1 No

what is scour depth $ what's the process to determine it?..

Answer / iamrk1293

Scouring can be defined as a process due to which the particles of the soil or rock around the periphery of the abutment or pier of the highway bridge spanning over a water body, gets eroded and removed over a certain depth called scour depth.
Hydraulic Engineering Circular (HEC) has published a manual in which the methods are mentioned some of which are empirical equations or graphs to estimate the scour depth based on the discharge, flow velocity or flow depth etc.

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

what is the ideal temparature for concrete?

5 Answers   HCL,


how to find quantity of total concrete, cement bags and sand. for any ratio

4 Answers   Jayabheri,


1.how to calculate 4*3 runner qty in cft. 2.how to calculate the nails qty.(column,beam,slab) 3.if any formula for binding wire qty calculation.

1 Answers   Gammon,


why does the most of civil engg is not intersted to going for teaching field?

1 Answers  


what are the tests conducted on cement,aggregate and concrete?briefly explain that tests procedure and limits adopted for safety side.

1 Answers   DLF, L&T,


how many shuttering material required for 1000 sq.m built up area.

1 Answers   ABC, CGHB,


Reinforcement details at hinged joint

1 Answers  


Required amount of Steel bars, cement/ square feet for roofing of residential building upto 3rd floor.

1 Answers   Sail,


how to calculate sand in CFT from a concrete foundation (m^3)???

1 Answers  


if there is no alternative of silty sand avail near ,then how it is used in cement mortar or concreting?

2 Answers  


Let suppose A building wall is 12 ft high and 30 ft long and labour cost is 100 rupee per feet so calculate the total cost of labour and also explain in detail...plz ans me immadiately i am hurry Thanx

1 Answers  


please tell me how to convert cubic feet to cubic meter

5 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4453)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)