Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


how we can calculate cable size of 230v,1 hp single phase
motor ? panel to motor distance is 25 meter

Answers were Sorted based on User's Feedback



how we can calculate cable size of 230v,1 hp single phase motor ? panel to motor distance is 25 met..

Answer / vaibhav v t

You can use 3 core x 1.5 sqmm copper cable.Upto 5 hp three
phase or single phase your can use this cable.

Is This Answer Correct ?    15 Yes 6 No

how we can calculate cable size of 230v,1 hp single phase motor ? panel to motor distance is 25 met..

Answer / abokamal

cable design.
first we have to choose CB.
(I)load=P/(V*PF)......... assume pf=0.8
(I)=746/(230*0.8)=4.1 Ampere
(I)cb=(I)load *s.f (FASETY FACTOR)=4.1*1.25=5.1 Ampere
(I)cable=(I)cb/D.F (DERATING FACTOR)=5.1/0.8=6.33 Ampere
from catalouge you can select the cable according to the
current.
you have to see (volt/ampere/meter) to see the voltage drop
limit which according to +-5%

Is This Answer Correct ?    9 Yes 1 No

how we can calculate cable size of 230v,1 hp single phase motor ? panel to motor distance is 25 met..

Answer / kumar

Mr.vaibhav your answer is standard or you find out by using
formula ?

Is This Answer Correct ?    2 Yes 1 No

how we can calculate cable size of 230v,1 hp single phase motor ? panel to motor distance is 25 met..

Answer / vipin

kamal is right ,after deciding the load current you ll have to consider the starting condition....
as per the IEEE regulations you ll have to consider 3 to 4 times the rated current as the starting current...as the rated current is coming around 6 amperes you can select a CB of 20A DP or SP. A 4sqmm cable will be std for the 1 hp pump.. you will have to verify with your supply company rules for the size of cable to be used for the designed value of circuit breaker.

Is This Answer Correct ?    3 Yes 2 No

Post New Answer

More Electrical Engineering Interview Questions

How Id and Ires are calculated in siprotech 7ut612 and abb trsfmr differential relay.what is the formula

1 Answers  


What is Electrical Engineering?

13 Answers   L&T, NTPC, Wockhardt,


what is humming noise and wha is the reason to develop humming noise in a mv pannel ?

2 Answers   HPL,


sir , what happen if we decrease ( approx 3 inch ) the lenth of shaft in 110KW Induction , three phase motor. actually a 110KW motor is couppled with star couplling to 120TR compressor. When we doing maintenance in compressor it is required to skid the motor backword and resulting dis- alightnment . so we want to change the tyre coupling in place of existing coupling. so it is required to cut off the rotor aprox 3 inch form driving side.

2 Answers  


What is the difference between EARTH & NEUTRAL?

13 Answers   L&T,


What do you mean by nominal ratio of instrument transformer?

1 Answers  


What are the two major types of control system?

0 Answers  


On load tap changer (OLTC) explode? Transformer Vector group: Ynd11 Rated Power: 353MVA Rated Current: 693A Voltage:294/20KV OLTC Type: T III Y1000 110/c 12193w Max Operation Current: 295A Step Voltage: 550V Arrangement in Tx windings: Y Connection Problem: Damage of Unit 1 Generator Transformer On Load Tap Changer (OLTC) Description of Incident: 9.00 a.m. :- Generator No Load test on excitation system started 10.30 a.m :- Carried out AVR change over test 11.30 a.m :- Preparation for Generator Manual Synchronizing test 12.00 a.m :- Manual Synshronizing test started. Observed incoming generator voltage higher than running voltage. CECR operator operated Generator Transformer OLTC to bring down the incoming generator voltage 12.03 a.m :-Generator Transformer abnormal alarm operated at Gen.Control Desk (CECR) CECR operater at Generator transformer bay informed that the transformer oil splashed out from OLTC. CECR operater informed that he heard explosion inside OLTC. Observed Oil level & Oil Flow alaram operated at Tranformer local annunciator. 12.05 am :- CECR operator 'Open Gen Field Breaker” 12.10 a.m. :- Elec1 team inspected the OLTC and found the OLTC rupture disk was broken and oil spilled at OLTC area. - Elec1 found the OLTC top cover bulging. Do anyone know why and possibility cause happen in this OLTC.

9 Answers  


What is plc.

2 Answers  


what is cogging and crawling

20 Answers   ABB, Ashok Leyland, Bharat Bijlee, BMRCL, MN Dastur, Siemens,


For 132 KV line, PT or CVT which is prefered for measuring & protection? is there any IS or IEE standard available?

1 Answers  


Can any body tell gulf interview question for experienced electrical engineer ?

0 Answers   Gulf,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)