Answer / priya
In the construction of RC buildings, due to the
limitations in available length of bars and due to
constraints in construction, there are numerous
occasions when column bars have to be joined. A
simple way of achieving this is by overlapping the two
bars over at least a minimum specified length, called
lap length. The lap length depends on types of
reinforcement and concrete. For ordinary situations, it
is about 50 times bar diameter. Further, IS:13920-1993
prescribes that the lap length be provided ONLY in the
middle half of column and not near its top or bottom
| Is This Answer Correct ? | 28 Yes | 2 No |
Answer / sjtbehera
Lap length are recquired when distance of structure is
larger than the length of Bars.
It is recquire to bind the two bars so that load can
carried.
| Is This Answer Correct ? | 6 Yes | 4 No |
Lap Length is 3/2 lap Lenths. Depends on Road
Length.Methods are 3/2. ItS Reqiured is very impotant
Reniforcement continous.
| Is This Answer Correct ? | 2 Yes | 9 No |
Dear Sir, I work in hydro project. I want to hire Scorpio/ Bolero on monthly basis. But how can i justified its amount (Hourly basic). Please solve my problem
As per Method of measurement how to calculate no of column stirrups (ie: upto slab bottom or beam bottom)
significance of specific surface area of particles?
how must steel will use for 1 cubic meter.formula of steel for beam,column,lantern.
17 Answers CCCL, Gulf Construction, KITECH, L&T, Mars Planning Engineering Services, NHAI, Simplex, Supertech, Yamaha,
how to calculate steel quantity in plinth beam&footing
plz tell me the compresive stength of genral con. & foam con. all grade after 7,14,21,28 day
IS THERE ANY JOBS FOR THOSE WHO ARE IN FINAL YAER OF ENGINEERING(CIVIL) IN MUMBAI
WHAT IS NON DESTRUCTIVE TEST?PLEASE GIVE ME THE PROCEDURE?
12 mm dia not available at site for raft, 10 mm are available at site how to calculate?
What is Leastcount of 1. Total station 2. Theodolite 3. Dumpy level 4. Plane Table
Which foundation is stronger, Pile or Standard?
08. 4 main points about check list for Shuttering works are––– 4 i) ii) iii) iv) 09. 4 main points about check list for Concreting works are––– 4 i) ii) iii) iv) 10. 4 main points about check list for Plaster works are––– 4 i) ii) iii) iv) 11. 4 main points about check list for Brick works are–– – 4 i) ii) iii) iv) 12. 3 main points about Project delaying factors are––– 3 i) ii) iii) 13. Write down 60-grade M.S. deformed bar specification. 3 14. 3000 psi concrete means: 1 15. 4 main points about methods of wastage control are–– – 4 i) ii) iii) iv) 16. 1 main point about reasons for your honesty is : 1 17. Water cement mixing in hopper less mixture machine is better than hopper mixture machine because: 1 18. 2 main points about your role during roof casting are–––– 2 i) ii) 19. a. The weight of 3333m deform bar of 24.5 mm dia is…… 1 b. The weight of 300 rft plain bar of dia 1 is……. 1 20. The types of slumps are––– 3 i) ii) iii) 21. 4 main points about the causes of cylinder failure are––– 2 i) ii) iii) iv) 22. Detection of a beam & a girder are–––– 2 i) ii) 23. Curing is needed for–––– 1 24. The types of slabs in respect of size & shape are––– 5 In respect of size: i) ii) In respect of Shape i) ii) iii) 25. The types of Column in respect of size & shape are–– – 9 In respect of size: i) ii) In respect of Shape: i) ii) iii) iv) v) vi) vii) 26. 3 field tests & 3 Laboratory tests of bricks are––– 6 Field tests: i) ii) iii) Lab test: i) ii) iii) 27. 2 field tests & 1 Laboratory tests of sand are––– 3 Field tests: i) ii) Lab test: i) 28. 1 field tests & 1 Laboratory tests of M.S rod are––– 2 Field tests: i) Lab test: i) 29. a. The % of water absorbs by brick chips: …………… 1 b. The % of water absorbs by Stone chips: …………… 1 30. In respect of design: 5 a. The % of strength gains by concrete in 28 days= b. The % of strength gains by concrete in 14 days= c. The % of strength gains by concrete in 07 days= d. The % of strength gains by concrete in 03 days= e. The % of strength gains by concrete in 28 days without curing =
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)