Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


what is lap length? why it is required?

Answers were Sorted based on User's Feedback



what is lap length? why it is required? ..

Answer / priya

In the construction of RC buildings, due to the
limitations in available length of bars and due to
constraints in construction, there are numerous
occasions when column bars have to be joined. A
simple way of achieving this is by overlapping the two
bars over at least a minimum specified length, called
lap length. The lap length depends on types of
reinforcement and concrete. For ordinary situations, it
is about 50 times bar diameter. Further, IS:13920-1993
prescribes that the lap length be provided ONLY in the
middle half of column and not near its top or bottom

Is This Answer Correct ?    28 Yes 2 No

what is lap length? why it is required? ..

Answer / sjtbehera

Lap length are recquired when distance of structure is
larger than the length of Bars.
It is recquire to bind the two bars so that load can
carried.

Is This Answer Correct ?    6 Yes 4 No

what is lap length? why it is required? ..

Answer / deoghar

Lap length is required for tie up with same bar for continuity of the role or steel.

Lap length : 50d 

Is This Answer Correct ?    0 Yes 0 No

what is lap length? why it is required? ..

Answer / om prakash narayan

Lap Length is 3/2 lap Lenths. Depends on Road
Length.Methods are 3/2. ItS Reqiured is very impotant
Reniforcement continous.

Is This Answer Correct ?    2 Yes 9 No

Post New Answer

More Civil Engineering Interview Questions

Dear Sir, I work in hydro project. I want to hire Scorpio/ Bolero on monthly basis. But how can i justified its amount (Hourly basic). Please solve my problem

0 Answers  


As per Method of measurement how to calculate no of column stirrups (ie: upto slab bottom or beam bottom)

1 Answers  


significance of specific surface area of particles?

2 Answers  


how must steel will use for 1 cubic meter.formula of steel for beam,column,lantern.

17 Answers   CCCL, Gulf Construction, KITECH, L&T, Mars Planning Engineering Services, NHAI, Simplex, Supertech, Yamaha,


how to calculate steel quantity in plinth beam&footing

7 Answers   Enercon,


plz tell me the compresive stength of genral con. & foam con. all grade after 7,14,21,28 day

1 Answers  


IS THERE ANY JOBS FOR THOSE WHO ARE IN FINAL YAER OF ENGINEERING(CIVIL) IN MUMBAI

0 Answers  


WHAT IS NON DESTRUCTIVE TEST?PLEASE GIVE ME THE PROCEDURE?

3 Answers  


12 mm dia not available at site for raft, 10 mm are available at site how to calculate?

8 Answers  


What is Leastcount of 1. Total station 2. Theodolite 3. Dumpy level 4. Plane Table

3 Answers  


Which foundation is stronger, Pile or Standard?

6 Answers  


08. 4 main points about check list for Shuttering works are––– 4 i) ii) iii) iv) 09. 4 main points about check list for Concreting works are––– 4 i) ii) iii) iv) 10. 4 main points about check list for Plaster works are––– 4 i) ii) iii) iv) 11. 4 main points about check list for Brick works are–– – 4 i) ii) iii) iv) 12. 3 main points about Project delaying factors are––– 3 i) ii) iii) 13. Write down 60-grade M.S. deformed bar specification. 3 14. 3000 psi concrete means: 1 15. 4 main points about methods of wastage control are–– – 4 i) ii) iii) iv) 16. 1 main point about reasons for your honesty is : 1 17. Water cement mixing in hopper less mixture machine is better than hopper mixture machine because: 1 18. 2 main points about your role during roof casting are–––– 2 i) ii) 19. a. The weight of 3333m deform bar of 24.5 mm dia is…… 1 b. The weight of 300 rft plain bar of dia 1&#61618; is……. 1 20. The types of slumps are––– 3 i) ii) iii) 21. 4 main points about the causes of cylinder failure are––– 2 i) ii) iii) iv) 22. Detection of a beam & a girder are–––– 2 i) ii) 23. Curing is needed for–––– 1 24. The types of slabs in respect of size & shape are––– 5 In respect of size: i) ii) In respect of Shape i) ii) iii) 25. The types of Column in respect of size & shape are–– – 9 In respect of size: i) ii) In respect of Shape: i) ii) iii) iv) v) vi) vii) 26. 3 field tests & 3 Laboratory tests of bricks are––– 6 Field tests: i) ii) iii) Lab test: i) ii) iii) 27. 2 field tests & 1 Laboratory tests of sand are––– 3 Field tests: i) ii) Lab test: i) 28. 1 field tests & 1 Laboratory tests of M.S rod are––– 2 Field tests: i) Lab test: i) 29. a. The % of water absorbs by brick chips: …………… 1 b. The % of water absorbs by Stone chips: …………… 1 30. In respect of design: 5 a. The % of strength gains by concrete in 28 days= b. The % of strength gains by concrete in 14 days= c. The % of strength gains by concrete in 07 days= d. The % of strength gains by concrete in 03 days= e. The % of strength gains by concrete in 28 days without curing =

3 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4453)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)