Answer / mohd rashid
Calculate the x sectional area of the 12mm dia bars
Then calculate the no of 10 mm dia bar keeping the x sectional area same as of 12mmdia bar..place increased no of 10 mm dia bar in the given lenghtn breadth with new spacing.
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / paras bhanushali
calculate the 12mm dia bars total weight with spacing .
according to 10mm dia bars weight describe .
and spacing done
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / mohammed imtiaz
Required Ast/ Cs of area of bar to be provided(10mm).
for ex: no.of bars for T12 = 20nos (Req ast=2261.94sqmm)
No.of bars for T10= 2261.94/78.53
= 29
Hence we can provide 29 nos of T10 instead of 20T12.
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / vaideeswaran
T12 = 140 c/c, ( As per Dwg)
T10(site availability) = (Spacing ?)
Unit Weight of T12 = 0.888 , T10 = 0.616.
0.616/0.888 = 0.693% times lower than T12 ,
0.693 x 140 mm = 97.117 , Say = 97 mm c/c.
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / stejith
dimension of the area not mentioned. or if the weight of 12mm bars are known we can calculate the total 12mm full rod bars needed.
| Is This Answer Correct ? | 3 Yes | 4 No |
Answer / ameen salim
Measurements of slab and spacing of 12mm steel is not Mentioned in your question,
At first you have to calculate area of steel (Ast) designed by the structural engineer for that particular area (from structural drawing you can calculate). Then placed the 10 mm steel instead of 12 mm steel as per Ast you got.
Note:
Adjust the spacing as per Number of steel (10 mm) you have to placed as per calculation.
| Is This Answer Correct ? | 3 Yes | 4 No |
Answer / sitaram sharma
Calculate as per following formula.
ND1=ND2
Where N1 is the Number of D1 ( Dai) Bars and N2 is the Number of D2 ( Dai ) Basrs
| Is This Answer Correct ? | 2 Yes | 9 No |
water leak detection system question & answer
What is labour rate per kg for cutting,fixing and binding of reinforcement steet..??
3 Answers GKC Projects Limited GKCPL,
What are the Tests required to check the Quality of bar?
How to calculate the load of partion in flat slab if we use brick?
0 Answers CE, Mahalaxmi Developers,
what is the minimum SBC of soil is required for different types of soil?
if L*B*H = 20 then direct no of bricks =20 *500
how to calculate detail quantity of bricks and mortar for 500 cu.ft masonry work. consider wall thickness 9 inches
how much % of steel use in footing, slab, column
how to convert sand from Cum to Brass
what is the list of building construction equipment & teir output?
how many 10mm steel are needed in 99sqft room
how to calculate cement coefficient for 20mm thick vitrified tiles flooring with cm 1:4 with explaination
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)