12 mm dia not available at site for raft, 10 mm are available at site how to calculate?
Answers were Sorted based on User's Feedback
Answer / mohd rashid
Calculate the x sectional area of the 12mm dia bars
Then calculate the no of 10 mm dia bar keeping the x sectional area same as of 12mmdia bar..place increased no of 10 mm dia bar in the given lenghtn breadth with new spacing.
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / paras bhanushali
calculate the 12mm dia bars total weight with spacing .
according to 10mm dia bars weight describe .
and spacing done
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / mohammed imtiaz
Required Ast/ Cs of area of bar to be provided(10mm).
for ex: no.of bars for T12 = 20nos (Req ast=2261.94sqmm)
No.of bars for T10= 2261.94/78.53
= 29
Hence we can provide 29 nos of T10 instead of 20T12.
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / vaideeswaran
T12 = 140 c/c, ( As per Dwg)
T10(site availability) = (Spacing ?)
Unit Weight of T12 = 0.888 , T10 = 0.616.
0.616/0.888 = 0.693% times lower than T12 ,
0.693 x 140 mm = 97.117 , Say = 97 mm c/c.
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / stejith
dimension of the area not mentioned. or if the weight of 12mm bars are known we can calculate the total 12mm full rod bars needed.
| Is This Answer Correct ? | 3 Yes | 4 No |
Answer / ameen salim
Measurements of slab and spacing of 12mm steel is not Mentioned in your question,
At first you have to calculate area of steel (Ast) designed by the structural engineer for that particular area (from structural drawing you can calculate). Then placed the 10 mm steel instead of 12 mm steel as per Ast you got.
Note:
Adjust the spacing as per Number of steel (10 mm) you have to placed as per calculation.
| Is This Answer Correct ? | 3 Yes | 4 No |
Answer / sitaram sharma
Calculate as per following formula.
ND1=ND2
Where N1 is the Number of D1 ( Dai) Bars and N2 is the Number of D2 ( Dai ) Basrs
| Is This Answer Correct ? | 2 Yes | 9 No |
Curing time for 1)R.C.C slab 2)B.W 3)Plastering
How to increase a bearing capacity of soil?
What is unit weight of normal concrete?
How to come 1.54 from dry to wet concrete?
Target strength = fck +(1.65*4) What is this 4
for gravel roads in India to get 1feet height how much height we have to fill
what is mean by bPo in construction? pls tell me
What happens when water mixed with cowdung is used for priming instead of water for lifting water in pumps?
Difference between Statics, Dynamics, Kinetics, Kinematics
DESIGN PROCEDURE OF THE COLUMNS
please send me bhel questions on rupesh.017@rediffmail.com
From where the relationship of target strength comes in mix design(graph)
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)