Answer Posted / priya
In the construction of RC buildings, due to the
limitations in available length of bars and due to
constraints in construction, there are numerous
occasions when column bars have to be joined. A
simple way of achieving this is by overlapping the two
bars over at least a minimum specified length, called
lap length. The lap length depends on types of
reinforcement and concrete. For ordinary situations, it
is about 50 times bar diameter. Further, IS:13920-1993
prescribes that the lap length be provided ONLY in the
middle half of column and not near its top or bottom
| Is This Answer Correct ? | 28 Yes | 2 No |
Post New Answer View All Answers
natucher of concrete &type of concrete?
how to convert cement, sand aggregate quantity from M3 to kg with full description?
what is the minimum cement content for M20 & M25 as per is code -456(2000).
how to nfind out the specific gravity of sand.aggregate,water please help...
by which materials we can prepare circular shuttering with tentative cost of material(rate analysis)
What is meaning of tlc
What is passive earth pressure ?
What is oneside mat. And explain
is basic cost of the material includes tax?
very simple or less time consuming formula for reinforcement calculation by moment
what will be the cost of thickness of 125mmor rcc measurement of 52x33.75 feet
What is c.g.i sheet which used for roof??
I am a civil engineering student and going to attend interview in this week in an IT company.Will they ask me questions about my area of interest or cs
Can we apply curing compound on ceiling (slab Bottom)
How will you reduce the concrete flow after mixing the concrete