Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


Q1) I am having an interview in a construction company for
a large sewage project . Since I have not done any such
project , there are some queries from my end. Pls. help me
to solve them. I will be thankful to you :-

a) Normally for large project 400-600 houses & around
1600 peoples , how much dia pipe is used and which type of
pipe is used?
b) For trenching , I have heard that IS 1200 implies,
what are the rules of calculating earthwork in case of
depth of 2m or above ?
c) To prevent soil to fall when depth of trench is
more , what steps are taken and how there qty. is
calculated . Like I have heard about timbering . what is
this ?
d) What are the rules for disposing off the excavated
soil ?
e) How the pipes that are used are being jointed?
f) In case of cleaning on choks , is there any
intermediate things provided?
g) For foul gases any outlets are provided thru out
length of pipeline?
h) What is the flow digram like from houses thru small
pipe to main pipeline than where main pipeline disposes
wastage ?
i) Any other thing that has to be kept in mind while
calculating earth work for excavation like steps are made
and other things? How earthwork is calculated in case of
steps ? Pls. explain with a sketch.


Regards,



Q1) I am having an interview in a construction company for a large sewage project . Since I have..

Answer / sjtbehera

Ans1. +generally raw water from house to treatment plant CI
pipe are used. is maximum 600 Dia. in plant maximum 200 dia
re used. HDPE pipe are used.

ans - calculating earthwork is based on site condition.
although some rules are provided in IS 1200, but it is
better to calculate in site. below 2mm avg. calculation are
done

ans-for falling of earth scour are applied. this means some
protection done for sliding soil to the trench. it is aform
of net, tina fixing or sand bags are provided.

Ans- disposal of earth from site not follow some basic
rule. Calculate filling earth. volume of this earth are
store in suitable site. rest you disposal according site
incharge.

ans- pipes are joint in collar joints or welding

ans- choks are omitted by manual or by pressure

ans- no vent pipre are not provided in pipe. sweage dirctly
transfer to treatment plant. air ventilation pipe are
provided for air pressure.

ans- sorry this page are not allow to draw sketch

Is This Answer Correct ?    2 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

what is the weight of one cubic meter M20 concrete ?

10 Answers  


Whats be the minimum foundation depth of multistoried building as per height of building in individual footing?

0 Answers  


at the beam-column junction point tell me how much beam bars should pass through column ring ? 3 or 2 or 1 . answer with reason. if it is not happen then what will be he effect ?

1 Answers  


what are the Task work of different labour.?

0 Answers  


While calculating quantity of cement required for 1 qubic meter If mix is m25 1:1:2 =4 1.52/4=0.38, 0.38x1440=547.20 kgs I know 1440 is unit weight of cement And what is 1.52 ? And some one using 1.54 and 1.53 etc... Why they are using can u explain me what is 1.52, 1.53, 1.54?

4 Answers  


what is working drawing?why it is use?

3 Answers  


How can calculate cement quantity in brick work

2 Answers  


How much cements bag (or in KG) required for 1 Sq. M concrete, for M-30 grad concrete as per CPWD and where is thr proof on site

0 Answers  


contractor receive 100 MT steel.after compliting the work the contractor refund 90 MT steel.How reconsilation of steel done?

0 Answers  


is ther any formule for w/c ratio

0 Answers   L&T,


How and where are aqueducts built?

0 Answers  


Are you good at detailing and explain about the project you have worked on detailing?

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)