Answer / naresh thakur
500 no. of bricks(brick size - 20cm.*10cm.*10cm.) required
for 1 cum of brick masonry.
and suppose, ratio = 1:6
then , sum = 1+6 = 7
as we know, total dry mortar required for 1 cum. of brick
masonry = 0.30 cum.
therefore following dry matrial required.
cement = 1* 0.30/7 = .04 cum. *28.8 = 1.15 bags.
sand = 6* 0.30/7 = 0.26 cum.
or 0.26 cum. * 35.3 = 9.18 cft.
Material required for 1 cum. of brick masonry in mortar
ratio of 1:6.
cement = 1.15 bags.
sand = 9.18 cft.
bricks = 500 nos.
| Is This Answer Correct ? | 316 Yes | 54 No |
Answer / aamir mushtaq shah
496 Bricks of nominal size 9"x4"x3" are required in 1 cum in
1:6 mortor
| Is This Answer Correct ? | 53 Yes | 11 No |
Answer / mahendra mohan srivastava
Mr naresh is given right answer based on standard brick
20.10.10
but we are using in construction 23.11.7 then we cuse 520
brick.
| Is This Answer Correct ? | 45 Yes | 19 No |
Answer / shanmugam
theroritically it is 500, but practically it is 490 bricks required for 1 cu-m,
when you go feet and inches for 1 cft it is around 14.5 nos
| Is This Answer Correct ? | 28 Yes | 13 No |
Answer / bhavya
can u tell me how this practical and theoritical value is different???
| Is This Answer Correct ? | 19 Yes | 9 No |
Answer / akbar_u2u
how many men days of loburs and masons are requirete for 1
cum,pcc (1:2:4),Pcc(1:3:6) and Pcc(1:4:8)
thanking you
| Is This Answer Correct ? | 17 Yes | 7 No |
Answer / farhat abbas naqvi
As thickness of motar is not uniform it should be
taken as 32% instead of 30%.To level the top masons
usually use motar more than 1cm as it should be.
| Is This Answer Correct ? | 10 Yes | 2 No |
Answer / abdur rahman
1cm=35.32 cft
normal size of brick=.75*.375*.25=.0703
if volum 35.32cft
morter.30%
morter=35.32*.30=10.59
brick=35.32-10.59=24.724/.0703=351bricks
ratio 1;6=7
1/7*10.59*1.27/1.25=1.54 cement
6/7*10.59*1.27=11.52 cft sand
| Is This Answer Correct ? | 17 Yes | 12 No |
Answer / sobhanbabu
theritically 500 bricks and practically 450 to 480.here
practically means type of skilled mason and labor.it needs
58 kg cement to construct a cumec of brick work of size
19*9*9cm
| Is This Answer Correct ? | 13 Yes | 11 No |
Hi is it any equation or relationship that describe the stress-strain diagram in concrete deep beam?
I want to know the material required per square foot in rcc roof. i.e. steel: kg/foot, cement/foot etc.
rate analysis,what is PERT, TMT ,UPVC
How to decide/consider the grade of bitumen for dbm.
what is spt
I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
Hi all, need Staad Pro V8i tutorial
Whats the difference between uniaxial column
what do you mean by ssd how it calculated
Dear Sir , I have my diploma in civil engineering in distance mode, so can i do my B.teck in regular stream . kindly suggest Regards Ramakrishna
what cement consumction plaster 15mm think per sqmt 1:3&1:6 how much kg.
What is the quantity of cement in mix m20 concrete?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)