Answer / n rajesh guttedat
In 7 days compressive strength must be 65% of 28 days strength
| Is This Answer Correct ? | 10 Yes | 2 No |
Answer / sjtbehera
compressive strength of 28 days or 7 days can be obtained
from compresseve testing machines. but As per IS code
minimum strength can not beyond strength of 28 days or 7
days
example- M 25= after 28 dyas strength should be 25 N/MM2
| Is This Answer Correct ? | 5 Yes | 5 No |
How to calculate cement and river sand material Qty for waterproofing base coat and finish coat
HOE TO YOU PLAN TO ACCHIEVE THE GOALS?
i wanted to know the quantity of cement and water cement ratio for 150mm*150mm*150mm mould.Grade of concret m20
what is the density of steel
10 Answers NGO, PWD, Sepco,
is excessive curing for brick work is good or bad for the walls?
What is the Null Point of chimney in Power Plant
define formwork
one litre of shuttering oil how much area covered the shuttering?
pls tell me , what is the water content
How to calculate quantity of binding wire for any kind of structures. How to calculate quantity of nails in 1 sq m shuttering.
how to estimate plastering quantity if the given object is in circular. 12 mm thick both side 1:3 example= i have 8.15 m2 how to estimate quantity
What is the Cement: sand: aggregate: water ratio for grade 30 (G30) concrete.
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)