How to calculate the compressive strength of 28 days of
concrete where we have 7 days compressive strength?
Answers were Sorted based on User's Feedback
Answer / n rajesh guttedat
In 7 days compressive strength must be 65% of 28 days strength
| Is This Answer Correct ? | 10 Yes | 2 No |
Answer / sjtbehera
compressive strength of 28 days or 7 days can be obtained
from compresseve testing machines. but As per IS code
minimum strength can not beyond strength of 28 days or 7
days
example- M 25= after 28 dyas strength should be 25 N/MM2
| Is This Answer Correct ? | 5 Yes | 5 No |
in 100 cft = 1350 bricks in 100 cft = ? bloks
how to calculate quantity of bricks in circular manhole with examples.
How to make a c++ program that converts any base to base 10?
what is mixed design, define it? what is way beecher?
How do we get this formula Ast=(0.5Fck/Fy) into(1-(in sqrt(1-((4.6Mu)/Fck.bd^2))into bd Fck=grade of cement i.e M25, M20 Fy=grade of steel i.e.Fe415,Fe250 Mu=moment b=width d=depth
What is Paste :
cement mortar1:5 12mm thick and one bags cement how much area pleastering please give anwser
12 Answers DeSigns Inc, L&T, Marg, Sand, Vee Technologies,
difference between specification and method of statement
What do you mean by the word 'shear'?
In case of columns the cover is from main steel or from stirrup & which is the IS code mentioned in it?
How to rectify thermal cracks (2mm wide, 9mm deep aprx. ) developed in tremix finished concrete floor?
what is the difference between np2, np3 & np4 rcc pipes
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)