what is the real de-shuttering time for rcc column,slaband
wall
Answers were Sorted based on User's Feedback
Answer / shishir bhansali
rcc column 12 hours
rcc slab depending upon the span. from 5 days to 14 days
rcc wall 12 hours
| Is This Answer Correct ? | 29 Yes | 3 No |
Answer / ravi kant sharma
Minimum 16 to 18hr for column for any grade of r.c.c.
| Is This Answer Correct ? | 8 Yes | 0 No |
Answer / royalcivil
the de-shuttering time for the slab is 21 days must.
for the column it should be minimum of 1 week
| Is This Answer Correct ? | 10 Yes | 26 No |
What are the RISKS during the project construction?
what is escalation?how it is done?
What is the DENSITY of 20mm Course aggregate?
how to estimate plastering quantity if the given object is in circular. 12 mm thick both side 1:3 example= i have 8.15 m2 how to estimate quantity
how would you describe yourself and your ideal job
how to find quantity of concrete in PCC M15
1. What is difference between auto level & dumpy level?
2 Answers Qatar Airlines, Sita Homes,
What is the finess modulus of sand?
what is pile and deam foundation
Sand density
undisturb samples are obtained by direct excavation thin walled sampler thick walled sampler none of this
where vr providing singly reinforced beam. i want to know the location of it in a building
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)