Answer / mallikarjuna
M10,M15(P.C.C)
M20,M25,M30,M35,M40(using OPC)
M50,M60,M75(using micro silica)
Is This Answer Correct ? | 399 Yes | 65 No |
Answer / kiran babu t
M5, M10,used for P.C.C and now a days M15 grade of concrete
has been widely used for PCC.
Where as M20,M25 used for footings,columns,beams&slabs.
From M30 grade of concrete onwards it is Design Mix
M30,M35,M40,M45,M50,M55,M60,M65,M70,M75,M80.
Is This Answer Correct ? | 306 Yes | 47 No |
Answer / sandeep kumar
For Lean Concrete = M-5,M-7.5,M-10,M-15
For RCC Concrete = M-20,M-25,M-30,M-35
For Coloumn, Pier etc = M-40,M-45,M-50,M-55
For High Grade of Concrete = M-60,M-70,M-75,M-80,M-90,M-100
Is This Answer Correct ? | 199 Yes | 47 No |
Answer / hanishsehgal
M20, M 25, M30 , M35 , M40 , THESE GRADES ARE USED IN
ORDINARY BUILDINGS AND THEY ARE DEPEND ON THE LOAD OF THE
BUILDINGS
M45 , M50 .
FOR R.C.C - M20 , M25 , M30 , M35
FOR COLOUMN - M40 , M45 , M50
Is This Answer Correct ? | 145 Yes | 29 No |
Answer / harsha
Ordinary Concrete M10, M15, M20
Standard Concrete M25, M30, M35, M40, M45, M50
High Strength Concrete M55, M60, M65, M70, M75, M80
Is This Answer Correct ? | 116 Yes | 15 No |
Answer / rajeshwar mishra
M15,M20,M25,M30,M35,M40 ACCORDING TO THE PLANNED STRUCTURE
Is This Answer Correct ? | 72 Yes | 13 No |
Answer / sunil khairnar
Depends on Mix Proportions. (i.e. 1:2:4, 1:1.5:3 etc.)
Is This Answer Correct ? | 78 Yes | 23 No |
Answer / v.ramachandraiah
The meaning of the Grade of concrete is charactorstic
compressive srenth of the 150mmx150mmx150mm concre cube at
28 days age
Is This Answer Correct ? | 30 Yes | 1 No |
what is directivity effect?
Are you good at detailing and explain about the project you have worked on detailing?
1.how to calculate 4*3 runner qty in cft. 2.how to calculate the nails qty.(column,beam,slab) 3.if any formula for binding wire qty calculation.
Explain what is structural frames or systems?
what is curtailment in rebars
in the footings first which reinforcement bar has to be layed as per design criteria.
2. In a container filled with each of the following materials, at a porosity of 40%, determine the upward gradient required to cause the quick condition (a) Lead shot with a G = 13.75; (b) Fibre beads with G = 2.15; (c) Sand with a G = 2.32
What is the use of array command?
minimum thickness of pcc 1;4;8 for road concrete
how to determine H- zone in a column? where it will occur?
Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quantity of concrete by explaining all formulas involved.