Answer / c. mak
Anchoring of reinforcing bars is necessary when the
development length of the reinforcement is larger than the
structure. Anchorage is used so that the steel's intended
tension load can be reached and pop-outs will not occur.
Anchorage shapes can take the form of 180 or 90 degree hooks.
| Is This Answer Correct ? | 67 Yes | 4 No |
Answer / kumar.k(kk)
The shapes can in form of L,U,staright usually devalopment
length is taken as the given tension value of such grade of
concrete
| Is This Answer Correct ? | 7 Yes | 4 No |
Answer / akhilesh chandra
If the actual available length is inadequate for full development, special anchorages must be provided, such as cogs or hooks or mechanical end plates.
| Is This Answer Correct ? | 2 Yes | 0 No |
Answer / kirishnasekar m
It is assumed that a proper structural assessment of the
structural elements to be subjected to the repairs will be
carried out by qualified engineers and that the choice of
the products and systems to be used, as well as the design,
is based on this assessment.
| Is This Answer Correct ? | 1 Yes | 4 No |
Answer / selvamani
ancorage bars are necessary to provide bond between the
concrete and the bars....
| Is This Answer Correct ? | 5 Yes | 12 No |
Answer / r. s. verma
when horizental and vertical membres are combined and that
reinforcement is called anchorage bar it prevent to splite
from concrete its shape can be straight L , U as per
location
| Is This Answer Correct ? | 0 Yes | 8 No |
what would be the design load of R.C.C Cooling tower per cell.?
Why we take 162.2 in (d*d/162.2) to calculate weight of steel???
How do you derive the quantity of cement & sand in brick work construction in 1Meter cube, using CM 1:6 and bricks of size 19*9*9 cm
what"s the abbreviation for P.C.C? what"s the formula to calculate 1m3 P.C.C consumption?
2 Answers ACIL, L&T, Punj Lloyd Ltd, Rajshree Construction,
can you mail me detailed procedure,entire syllabus and practice papers of mpsc civil engineering branch.I am in third year now
what is the stripping time of beam?
what is mean by stripping?
what is FPS brick
What does civil status mean?
what is the mode of method of face bar measurement
what is the difference between np2 and np3 concrete mix
0 Answers Sri Matha Constructions,
How many number of bricks required for 1 cum & how much mortar quantity require for 1 cum
22 Answers Assurance, Campus Interview, R Tech Developers, Ramdev Construction, Synergy,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)